Residential Addition / Remodel Permit in Nunn, Colorado

Required for additions, basement finishes, kitchen/bath remodels, or any renovation involving electrical, plumbing, or structural modifications, doors/windows, or wall changes in the Town of Nunn. Governed by the 2018 IRC as locally amended; the Town publishes dedicated homeowner guides for Basement Finish and Home Additions scopes.

Verified 2026-07-23 · Source

When you need this permit

  • Planning Board approval required before SAFEbuilt review begins if the project involves a structure or addition over 120 sq ft
  • Submit one set of plans showing before-and-after conditions, square footage by area, and a detailed description of proposed use
  • If walls are proposed for removal, plans must address structural implications (per general IRC/IBC provisions on structural elements)
  • Any exterior egress window well added or altered must comply with IRC R310.2.3 dimension requirements as locally amended
  • All contractors performing electrical or plumbing work must hold a current Colorado DORA state license, verified by the Town per its Electrical/Plumbing License Contemporaneous Review Guidelines (HB19-1086)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Town Admin Fee (Building Permit, plan review required) + Use TaxCLOSED 2026-07-23 on a live primary source: the Town of Nunn's 'Fee Schedule, Effective January 22nd, 2026' (PDF, linked live from the Town homepage — not located in the prior 2026-07-06 chase) lists under 'Building Permits': 'Admin Fee (permits requiring plan review) $75.00' and 'Use Tax on all Building Permits 2%'. Additions/remodels are described in this file's own requirements as going through SAFEbuilt review regardless of size (only Planning Board approval is size-gated at 120 sq ft), so the plan-review tier governs. This is the Town Clerk's own flat admin fee and use-tax rate — charged IN ADDITION TO SAFEbuilt's separate valuation-based plan-review fee, which remains unpublished as a table (re-checked 2026-07-23).
$75.00 flat Admin Fee (permits requiring plan review), plus 2% Use Tax on all Building Permits

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Remodel Permit permit actually take in Nunn?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Framing / Trade Rough-Ins

    Framing, electrical, plumbing, and mechanical rough-ins before concealment, scheduled with SAFEbuilt

  2. 2

    Insulation

    Required if the scope adds or alters wall/ceiling/floor insulation or exterior windows

  3. 3

    Final Inspection

    All work complete per approved plans

See the full Nunn inspection guide — scheduling & re-inspection fees →

Tips

  • The Town publishes dedicated 2024 IRC homeowner guides for Basement Finish and Home Additions — review the applicable guide before assembling your submittal to avoid missing a scope-specific requirement.
  • A structural wall removal or egress window change can trigger additional review beyond a purely cosmetic remodel — flag any structural changes clearly on your application.

Frequently asked questions

Nunn requires a residential addition / remodel permit for: Planning Board approval required before SAFEbuilt review begins if the project involves a structure or addition over 120 sq ft; Submit one set of plans showing before-and-after conditions, square footage by area, and a detailed description of proposed use; If walls are proposed for removal, plans must address structural implications (per general IRC/IBC provisions on structural elements); Any exterior egress window well added or altered must comply with IRC R310.2.3 dimension requirements as locally amended; All contractors performing electrical or plumbing work must hold a current Colorado DORA state license, verified by the Town per its Electrical/Plumbing License Contemporaneous Review Guidelines (HB19-1086). If your project isn't listed, confirm with Town of Nunn Town Clerk's Office (Building/Planning) at 970-897-2385 before starting work.

In Nunn, the published Town Admin Fee (Building Permit, plan review required) + Use Tax is: $75.00 flat Admin Fee (permits requiring plan review), plus 2% Use Tax on all Building Permits. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Nunn does not publish a plan-review timeline for this permit. Contact Town of Nunn Town Clerk's Office (Building/Planning) at 970-897-2385 for current turnaround.

You'll need: Building Permit Application; Plans (before/after, floor plan with square footage). See the required-documents checklist on this page for details on each.

Nunn requires 3 inspection(s) for a residential addition / remodel permit, in order: Rough Framing / Trade Rough-Ins, Insulation, Final Inspection. Schedule each through Town of Nunn Town Clerk's Office (Building/Planning) (970-897-2385).

Apply through Town of Nunn Town Clerk's Office (Building/Planning) at 185 Lincoln Ave / P.O. Box 171, Nunn, CO 80648. Phone: 970-897-2385, email: kendra.minch@townofnunnco.gov. Office hours: Town of Nunn does not publish standing office hours on the Building/Planning page or Town Clerk page; general contact is 970-897-2385 / town.clerk@townofnunnco.gov. Nunn has no dedicated Building Department staff — the Town Clerk's Office intakes all building permit applications and coordinates with the Planning Board (for structures over 120 sq ft) and SAFEbuilt (contracted plan review and inspections).. Official information: https://townofnunn.colorado.gov/departments/building/planning.

Nunn, Colorado has adopted: 2018 International Building Code (IBC), chapters 1-33 and appendix chapter 1, adopted by reference — Nunn Municipal Code (NMC) 15.04.020, as amended (Ord. No. 237 12-18-2003; Ord. No. 263 5-3-2007; Ord. No. 317 6-20-2019); 2018 International Residential Code (IRC), chapters 1-43 and appendix chapters H and M, adopted by reference — NMC 15.04.120, as amended (Ord. No. 237, 263, 317); 2018 International Mechanical Code (IMC), chapters 1-15, adopted by reference — NMC 15.04.030 (Ord. No. 237, 263, 317); 2018 International Plumbing Code (IPC), chapters 1-13, adopted by reference — NMC 15.04.050 (Ord. No. 237, 12-18-2003); 2018 International Fuel Gas Code (IFGC), chapters 1-8, adopted by reference — NMC 15.04.090 (Ord. No. 237, 263, 317); 2018 International Existing Building Code (IEBC), chapters 1-16, adopted by reference — NMC 15.04.130 (Ord. No. 263 5-3-2007; Ord. No. 317 6-20-2019); 2018 International Property Maintenance Code (IPMC), chapters 1-8, adopted by reference — NMC 15.04.150 (Ord. No. 317 6-20-2019); 2018 International Swimming Pool and Spa Code (ISPSC), chapters 1-11, adopted by reference — NMC 15.04.160 (Ord. No. 317 6-20-2019); 2012 International Energy Conservation Code (IECC), chapters 1-5, adopted by reference as the town energy conservation code — NMC 15.04.140 (Ord. No. 317 6-20-2019); IBC section 1301.1.1/101.4.6 and IRC chapter 11 are both explicitly amended to substitute the 2012 IECC as well; National Electrical Code, 2002 edition, adopted by reference — NMC 15.04.040 (codified text, unamended since original Code 2002 codification). NOTE: this is the currently codified NEC edition in the 2024 Nunn Municipal Code as republished by Ordinance No. 326 (adopted 6-20-2024, adopting/enacting the Municipal Code by reference). However, SAFEbuilt's own current 'Photovoltaic System Submittal Requirements' handout (the Town's contracted plan-review/inspection agency) states 'Applicable current codes are the 2020 NEC, 2018 International Codes' — a direct discrepancy between the codified 2002 NEC text and SAFEbuilt's operational reference. Flagged honestly rather than resolved by assumption; the governing citation is the codified 2002 NEC per NMC 15.04.040 pending confirmation from the Town.; Chapter 15.16 (Energy Efficiency Construction) of the Nunn Municipal Code additionally references the 1977/1978 Colorado Model Energy Efficiency Construction and Renovation Standards for Nonresidential Buildings and the companion Colorado Recommended Energy Conservation 'Performance' Code for Residential Buildings — these appear to be vestigial/superseded provisions retained from the original 2002 code codification and predate the town's adoption of the 2012 IECC at NMC 15.04.140 (2019); not applied as the governing energy standard in this file.. Local amendments apply — see the Nunn overview page for the full list.

Only if the scope adds a structure or addition over 120 square feet. A straightforward interior basement finish with no exterior footprint change would not typically trigger Planning Board review, but would still require a building permit and SAFEbuilt plan review/inspection.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nunn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.