Solar Permit (Ground-Mounted and Roof-Mounted) — Village of Corrales, New Mexico · Requirements sheet
Verified 2026-07-05 · Source: https://www.corrales-nm.org/DocumentCenter/View/3488/building_permit_fees_and_rates_revised
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Permit (Ground-Mounted and Roof-Mounted) in Village of Corrales, New Mexico
Required for solar photovoltaic installations in Corrales. The Village's combined Application for Construction Permit distinguishes ground-mounted from roof-mounted systems, with a substantially higher flat fee for ground-mounted installations reflecting the additional structural/foundation and zoning review involved.
Verified 2026-07-05 · Source
When you need this permit
- A Construction Permit is required for solar installations; select 'Solar' as the type of application, specifying ground-mounted or roof-mounted
- Roof-mounted systems: $150.00 flat fee
- Ground-mounted systems: $250.00 flat fee
- Electrical connection/interconnection permitting and inspection for the solar system is handled separately through the City of Rio Rancho Building Department, consistent with Corrales' general MEP-trade referral
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection
Verifies mounting/anchoring per approved plans; electrical interconnection is separately inspected through the City of Rio Rancho
See the full Village of Corrales inspection guide — scheduling & re-inspection fees →
Tips
- Ground-mounted solar costs substantially more ($250.00 vs. $150.00 for roof-mounted) under the Village's flat-fee schedule — factor this into project cost comparisons early.
- The electrical interconnection permit for a solar system goes through the City of Rio Rancho Building Department, not the Village of Corrales — plan for two separate permitting tracks (Village for the mounting structure, Rio Rancho for the electrical connection).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Village of Corrales building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Village of Corrales
Solar Permit (Ground-Mounted and Roof-Mounted) in other cities
Compare solar permit (ground-mounted and roof-mounted) fees across New Mexico →
Look up this fee in a different city →
Now live
Build your Village of Corrales project checklist
Describe your project once and get every permit, document, and fee it triggers in Village of Corrales — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →