EV Charger / EVSE Permit — Mapleton, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://www.mapleton.org/Fee%20Schedule.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Mapleton, Utah
Mapleton does not publish a distinct EV-charger or general electrical-permit fee line item. Per the city's official FAQ, a building permit is explicitly required to 'erect, install, enlarge, repair, move, remove, convert or replace any electrical... system' — which covers EV charger/EVSE installation. Mapleton's Community Development Fee Schedule prices all such work not otherwise itemized (e.g., Solar/Wind, Basement Finish) under the general 'Building Permit Major' line: IBC valuation multiplied by a 0.005 factor.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- Building permit required per Mapleton's official FAQ: a permit is needed to 'erect, install, enlarge, repair, move, remove, convert or replace any electrical... system'
- Minor electrical repairs are exempt from permitting, but a new EV charger circuit/install is not a minor repair
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
Inspection of the installed circuit, panel work, and EVSE equipment prior to use; scheduled through the Building Department, (801) 489-6138.
See the full Mapleton inspection guide — scheduling & re-inspection fees →
Tips
- Mapleton has no distinct EV charger or general electrical-permit category — a permit is still required per the city's official FAQ ('erect, install... any electrical... system'), billed under the valuation-based Building Permit Major fee (0.5% of IBC valuation).
- Unlike Solar/Wind installs (flat $165) or Basement Finish (flat $300), EV chargers have no dedicated flat-fee category, so the general valuation-based fee applies.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mapleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mapleton
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →
Related guides