EV Charger / EVSE Permit in Mapleton, Utah

Mapleton does not publish a distinct EV-charger or general electrical-permit fee line item. Per the city's official FAQ, a building permit is explicitly required to 'erect, install, enlarge, repair, move, remove, convert or replace any electrical... system' — which covers EV charger/EVSE installation. Mapleton's Community Development Fee Schedule prices all such work not otherwise itemized (e.g., Solar/Wind, Basement Finish) under the general 'Building Permit Major' line: IBC valuation multiplied by a 0.005 factor.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • Building permit required per Mapleton's official FAQ: a permit is needed to 'erect, install, enlarge, repair, move, remove, convert or replace any electrical... system'
  • Minor electrical repairs are exempt from permitting, but a new EV charger circuit/install is not a minor repair

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Major (valuation-based, general electrical/mechanical/plumbing systems)Mapleton City Community Development Fee Schedule, 'Building' section: 'Building Permit Major — Based on IBC & .005 multiplier.' No EV-specific or separate electrical-trade line item is published; this is the general fee category covering electrical system installs per the city's FAQ. Contact the Community Development Department at (801) 489-6138 to confirm the valuation figure used for a specific EV charger installation.
Based on IBC valuation table, multiplied by a 0.005 factor
Special Inspection / Re-inspection FeeMapleton City Community Development Fee Schedule, 'Building' section: 'Special Inspection — $55.'
$55

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Mapleton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection of the installed circuit, panel work, and EVSE equipment prior to use; scheduled through the Building Department, (801) 489-6138.

See the full Mapleton inspection guide — scheduling & re-inspection fees →

Tips

  • Mapleton has no distinct EV charger or general electrical-permit category — a permit is still required per the city's official FAQ ('erect, install... any electrical... system'), billed under the valuation-based Building Permit Major fee (0.5% of IBC valuation).
  • Unlike Solar/Wind installs (flat $165) or Basement Finish (flat $300), EV chargers have no dedicated flat-fee category, so the general valuation-based fee applies.

Frequently asked questions

Mapleton requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property; Building permit required per Mapleton's official FAQ: a permit is needed to 'erect, install, enlarge, repair, move, remove, convert or replace any electrical... system'; Minor electrical repairs are exempt from permitting, but a new EV charger circuit/install is not a minor repair. If your project isn't listed, confirm with Mapleton City Community Development Department (Building Division) at (801) 489-6138 before starting work.

No distinct EV-charger fee is published. Mapleton's official FAQ states a building permit is required to install any electrical system, and the city's Community Development Fee Schedule bills such work under the general 'Building Permit Major' fee (IBC valuation x 0.005), since no EV-specific or general electrical-trade line item exists.

Mapleton does not publish a plan-review timeline for this permit. Contact Mapleton City Community Development Department (Building Division) at (801) 489-6138 for current turnaround.

You'll need: Building Permit Application (MyGovernmentOnline / mgoconnect.org). See the required-documents checklist on this page for details on each.

Mapleton requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through Mapleton City Community Development Department (Building Division) ((801) 489-6138).

Apply through Mapleton City Community Development Department (Building Division) at 125 West 400 North, Mapleton, UT 84664. Phone: (801) 489-6138, email: permits@mapleton.org. Office hours: Mon–Thu 8:00 AM – 5:30 PM, Fri 8:30 AM – 5:00 PM. Official information: https://www.mapleton.org/departments/community_development/building/index.php.

Mapleton, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026; not separately itemized on Mapleton's own Building/Fee Schedule pages, but applies statewide as part of the State Construction Code.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026. Mapleton's official Building Inspection Summary page confirms the Insulation inspection is checked against 'current IECC.'; 2024 International Existing Building Code (IEBC) — current statewide edition per Utah Code § 15A-2-103(1)(i), effective July 1, 2026; not separately itemized on Mapleton's own pages, but applies statewide.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide edition per Utah Code § 15A-2-103(1)(n), effective July 1, 2026; not separately itemized on Mapleton's own pages, but applies statewide.; Modular Building Institute Standards 1200 and 1205 — adopted statewide per Utah Code § 15A-2-103(1)(o); not separately itemized on Mapleton's own pages.; Utah House Bill 64 (2024) drywall-inspection change — per Mapleton's official Building Inspection Summary page: 'Effective March 1, 2024 only fire restrictive drywall inspections will be required per HB64.'. Local amendments apply — see the Mapleton overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mapleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.