Required for new single-family residential construction and any work regulated by the adopted 2021 IRC / 2024 IBC in Mapleton. Applications are submitted through the City's online MyGovernmentOnline (mgoconnect.org) portal. Mapleton's fee is calculated from the adopted IBC valuation table using a 0.005 multiplier, per the Community Development Fee Schedule.

Verified 2026-07-08 · Source

When you need this permit

  • New single-family residential construction
  • Any work regulated by the adopted 2021 IRC (Mapleton City Code Ch. 15.04)
  • Structural modifications regulated by the adopted 2024 IBC / 2021 IRC
  • Application submitted through the mygovernmentonline.org / mgoconnect.org online portal per Mapleton's official Building page
  • Restroom facility (site toilet) must be on site at time of Setback/Footing inspection, per the Building Inspection Summary

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Major (valuation-based)Mapleton City Community Development Fee Schedule, 'Building' section: 'Building Permit Major — Based on IBC & .005 multiplier.' Retrieved from mapleton.org/Fee%20Schedule.pdf (DocumentCenter timestamp 202409191052590). Exact per-square-foot valuation figures are set by the adopted ICC/IBC Building Valuation Data table referenced in the same fee schedule; contact the Community Development Department at (801) 489-6138 to confirm the current valuation table snapshot used for a specific application.
Based on IBC valuation table, multiplied by a 0.005 factor
Special Inspection / Re-inspection FeeMapleton City Community Development Fee Schedule, 'Building' section: 'Special Inspection — $55.' Confirmed also on the official Building Inspection Summary page: 'Failure to be ready at the time the inspection is scheduled will result in a re-inspection fee of $55.'
$55

Review timeline

Plan reviewTypical estimate — confirm current times with the Mapleton building department
~14–14 business days

How long did your Residential Building Permit permit actually take in Mapleton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Setback, Footings, and Site Toilet

    Placement on property based on required setbacks verified; inspection of excavation, forms and reinforcing steel prior to placement of concrete. Concrete-encased electrode (ufer) must be installed. Restroom facility must be on site. Per Mapleton's official Building Inspection Summary page.

  2. 2

    Foundation

    Inspection of forms and reinforcing steel prior to placement of concrete.

  3. 3

    Subgrade Foundation Insulation

    Inspection of thermal insulation installed below ground level on foundation walls and/or beneath the concrete slab.

  4. 4

    Temporary Power

    Inspection of temporary pedestal with grounding rod; all outlets GFCI protected.

  5. 5

    Suspended Concrete

    Inspection of forms and reinforcing steel prior to placement of concrete on all precast, cast-in-place floors, and porch caps.

  6. 6

    Under Slab (US) Plumbing, Electrical, and/or Mechanical

    Inspection of all underground or under-slab work prior to burial or concrete covering.

  7. 7

    Shear

    Inspection of all structural sheathing and foundation straps prior to installation of weather barrier; may be included with the 4-way inspection.

  8. 8

    4-way and Gas-line

    Inspection of framing and all roughed-in electrical, mechanical, fuel gas piping, and plumbing installations. All windows and exterior doors must be installed for this inspection.

  9. 9

    Weather Barrier / Stucco-Lath-Flashing

    Inspection of exterior weather barrier, window and door flashing, and other flashing prior to installation of siding, masonry, and roofing products. Stucco/Lath/Flashing performed after all flashings, vapor barrier, and lath are installed and all penetrations sealed.

  10. 10

    Permanent Power

    Inspection of electrical service panel prior to utility hook-up. Must have ground wire connected to concrete-encased electrode and one GFCI outlet connected inside the house.

  11. 11

    Insulation

    Inspection to ensure insulation, doors, windows, heating and cooling equipment meets current IECC.

  12. 12

    Drywall

    Effective March 1, 2024, only fire-restrictive drywall inspections are required per Utah HB64.

  13. 13

    Shower Pan

    Fill with water to within 1/2 inch of top for a minimum of 15 minutes.

  14. 14

    Final

    Inspection of completed structure prior to use or occupancy. All permits must have a final inspection. All items indicated on the plans as to be finished must be in place (kitchen cabinets, sinks, bathroom fixtures, etc.). No personal items other than construction tools/equipment may be placed in the building until occupancy is granted.

See the full Mapleton inspection guide — scheduling & re-inspection fees →

Tips

  • All inspections are scheduled through the www.mygovernmentonline.org applicant portal — request inspections up to three days in advance if a specific date/time is preferred, per Mapleton's official Building Inspection Summary page.
  • Mapleton's Building Division is open Mon–Thu 8:00 AM–5:30 PM and Fri 8:30 AM–5:00 PM.
  • A restroom facility (site toilet) must be present on site at the time of the Setback/Footings inspection.
  • Failure to be ready at a scheduled inspection triggers a $55 re-inspection fee, payable at the City Office (cash, card, or check) before further inspections resume.
  • Effective March 1, 2024, only fire-restrictive drywall inspections are required under Utah HB64 — general drywall inspections were eliminated statewide.
  • Mapleton has no distinct EV charger / EVSE permit type or fee: a full-text check of Mapleton's Community Development Fee Schedule (mapleton.org/Fee%20Schedule.pdf, PDF fetched and searched directly 2026-07-20) found zero mentions of 'EV,' 'electric vehicle,' 'charging station,' or 'EVSE,' and no standalone electrical-trade permit line item — the schedule lists only a general 'Building Permit Major' (valuation-based, IBC + .005 multiplier) line for building-related work. A residential EV charger install is expected to route through this same Building Permit fee as standard electrical work; confirm directly with the Building Division before applying.

Frequently asked questions

Mapleton requires a residential building permit for: New single-family residential construction; Any work regulated by the adopted 2021 IRC (Mapleton City Code Ch. 15.04); Structural modifications regulated by the adopted 2024 IBC / 2021 IRC; Application submitted through the mygovernmentonline.org / mgoconnect.org online portal per Mapleton's official Building page; Restroom facility (site toilet) must be on site at time of Setback/Footing inspection, per the Building Inspection Summary. If your project isn't listed, confirm with Mapleton City Community Development Department (Building Division) at (801) 489-6138 before starting work.

Per Mapleton's Community Development Fee Schedule, the 'Building Permit Major' fee is based on the adopted IBC valuation table multiplied by a 0.005 factor. Contact the Community Development Department at (801) 489-6138 to confirm the exact valuation-table snapshot applied to a specific project.

Mapleton has not published its own plan-review SLA. Utah Code § 10-20-909 requires Utah municipalities to complete plan review of a one- or two-family dwelling or townhome within 14 business days after a 3-business-day completeness screening period — this statutory floor applies absent a published local timeline.

You'll need: Building Permit Application (MyGovernmentOnline / mgoconnect.org). Depending on your project, Mapleton may also ask for: Utah State Owner/Builder Agreement Form. See the required-documents checklist on this page for details on each.

Mapleton requires 14 inspection(s) for a residential building permit, in order: Setback, Footings, and Site Toilet, Foundation, Subgrade Foundation Insulation, Temporary Power, Suspended Concrete, Under Slab (US) Plumbing, Electrical, and/or Mechanical, Shear, 4-way and Gas-line, Weather Barrier / Stucco-Lath-Flashing, Permanent Power, Insulation, Drywall, Shower Pan, Final. Schedule each through Mapleton City Community Development Department (Building Division) ((801) 489-6138).

Building permit applications must be submitted through Mapleton's online submittal program at mgoconnect.org (MyGovernmentOnline) — log in to an existing account or create a new account, per the City's official Building page.

Mapleton, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026; not separately itemized on Mapleton's own Building/Fee Schedule pages, but applies statewide as part of the State Construction Code.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026. Mapleton's official Building Inspection Summary page confirms the Insulation inspection is checked against 'current IECC.'; 2024 International Existing Building Code (IEBC) — current statewide edition per Utah Code § 15A-2-103(1)(i), effective July 1, 2026; not separately itemized on Mapleton's own pages, but applies statewide.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide edition per Utah Code § 15A-2-103(1)(n), effective July 1, 2026; not separately itemized on Mapleton's own pages, but applies statewide.; Modular Building Institute Standards 1200 and 1205 — adopted statewide per Utah Code § 15A-2-103(1)(o); not separately itemized on Mapleton's own pages.; Utah House Bill 64 (2024) drywall-inspection change — per Mapleton's official Building Inspection Summary page: 'Effective March 1, 2024 only fire restrictive drywall inspections will be required per HB64.'. Local amendments apply — see the Mapleton overview page for the full list.