EV Charger / EVSE Permit in Saratoga Springs, Utah
Saratoga Springs City's Consolidated Fee Schedule has no distinct "EV Charger" or "EVSE" line item — confirmed via a full-text search of the entire document. EV charger/EVSE installation falls under the city's standard Electrical Permit process: a $22.00 Issuance of Electrical Permit Fee (not charged when the electrical permit is issued together with a building permit), plus a 25% Plan Review Fee and 1% State of Utah Inspector Training Fee. The city's separate EVSE Charging Stations page describes only its own public charging stations ($1.00/hour usage rate) and does not address private installation permitting.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Saratoga Springs
- Work performed per Saratoga Springs' adopted electrical code
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Saratoga Springs Consolidated Fee Schedule (Res. Show full citationHide
Saratoga Springs Consolidated Fee Schedule (Res. R21-46, 7-6-21), Building — Electrical Permit Fees: "Issuance of each Electrical Permit Fee — $22.00/each." Not charged when the electrical permit is issued in conjunction with a building permit. No distinct EV Charger or EVSE fee category exists anywhere in the schedule (confirmed via full-text search).Review timeline
Inspection process
- 1
Electrical Inspection
Inspection of the charger circuit, panel, and grounding by Saratoga Springs City.
See the full Saratoga Springs inspection guide — scheduling & re-inspection fees →
Tips
- Saratoga Springs has no separate EV Charger fee category — file under the standard Electrical Permit ($22.00 issuance fee, waived if bundled with a building permit).
- Don't confuse the city's public EVSE Charging Stations page (describing its own $1.00/hour public chargers) with private installation permitting — that page does not cover permits.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Saratoga Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Saratoga Springs's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Saratoga Springs yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Saratoga Springs lands. Privacy.
Other permits in Saratoga Springs
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Saratoga Springs project checklist
Describe your project once and get every permit, document, and fee it triggers in Saratoga Springs — in one checklist. Free, for any city and any number of projects.
Get started →