Mechanical / HVAC Permit in St. George, Utah
Required for heating, ventilation, and air conditioning installations, replacements, and ductwork modifications in St. George. Governed by the 2024 International Mechanical Code (IMC) as adopted by Utah Code § 15A-2-103(1)(e), current as of 7/1/2026 (the 2021 IMC governed through 6/30/2026).
Verified 2026-07-23 · Source
When you need this permit
- Furnace or boiler installation or replacement
- Air conditioning system installation or replacement
- Ductwork installation or major modification
- Evaporative cooler installation
- Fireplace or gas appliance installation (may also require a gas line permit)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support; IRC Equipment and Duct Plan must be on-site
- 2
Final
Equipment operational, Manual J/S/D verified, gas pressure tested, thermostat functional, combustion air supply verified; carbon monoxide detector required on every habitable level per St. George's inspection requirements
See the full St. George inspection guide — scheduling & re-inspection fees →
Tips
- Like-for-like furnace and AC replacements in St. George still require a mechanical permit at a minimum fee of $60.60.
- Manual J (loads), Manual S (equipment sizing), and Manual D (duct sizing) calculations are required per IRC § M1401.3 and M1601.1 as enforced in St. George — the city provides an IRC Equipment and Duct Plan form.
- Carbon monoxide detection — one detector per habitable level — is required per the St. George Residential Final Inspection Checklist.
- St. George follows the 2024 IMC, current as of July 1, 2026 (the 2021 IMC governed through June 30, 2026).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the St. George building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in St. George
Mechanical / HVAC Permit in other cities
Compare mechanical / hvac permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your St. George project checklist
Describe your project once and get every permit, document, and fee it triggers in St. George — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →