Basement Finish Permit in St. George, Utah
Required for finishing or remodeling an unfinished basement in St. George, including framing, electrical, plumbing, and mechanical work.
Verified 2026-07-23 · Source
When you need this permit
- Framing walls in an unfinished basement
- Adding a bedroom (requires egress window — 5.7 sq ft minimum opening, sill no higher than 44 inches above floor)
- Adding a bathroom (requires separate plumbing permit)
- Electrical wiring for new rooms
- Any structural modifications
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Assessed on project valuation per St. George's published 1997 UBC building permit fee schedule (sgcityutah.gov Building Fee Sheet PDF). Show full citationHide
Assessed on project valuation per St. George's published 1997 UBC building permit fee schedule (sgcityutah.gov Building Fee Sheet PDF). No separate basement-finish-specific flat fee is published; the valuation table itself is the grounded fee. Minimum $60.60; plan check 65%; D.O.C. 1%Review timeline
Inspection process
- 1
Framing
Wall framing, fire blocking, egress window openings and window wells
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls before drywall
- 4
Final
Drywall, fixtures, and all finishes complete; smoke detectors and carbon monoxide detectors (one per habitable level) installed per St. George's Final Inspection Checklist items 20–21
See the full St. George inspection guide — scheduling & re-inspection fees →
Tips
- Every basement bedroom in St. George requires an egress window — 5.7 sq ft minimum opening, sill no higher than 44 inches above the floor, per IRC enforced in St. George.
- Window wells deeper than 44 inches require a permanently attached ladder or steps per the adopted IRC.
- The furnace/water heater room needs adequate combustion air — do not fully enclose it without proper air supply openings.
- Smoke detectors are required in every bedroom, outside sleeping areas, and on every level (item 20 of St. George Final Inspection Checklist); carbon monoxide detectors are required on every habitable level (item 21).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the St. George building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
St. George's permit history is searchable by address
25,627 permits in our copy of St. George's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything St. George has issued.
25,599 of these 25,630 permits — 99.9% — carry an issued date, and those run from 1970 to 2026. The remaining 31 have no date at all.
Other permits in St. George
Basement Finish Permit in other cities
Compare basement finish permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your St. George project checklist
Describe your project once and get every permit, document, and fee it triggers in St. George — in one checklist. Free, for any city and any number of projects.