Residential Building Permit in St. George, Utah

Required for new residential construction, additions, and structural alterations in St. George.

Verified 2026-06-27 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit (1997 UBC valuation scale)$23.50 (up to $500); $23.50 + $3.05/each $100 over $500 (to $2,000); $69.25 + $14/each $1,000 over $2,000 (to $25,000); $391.75 + $10.10/each $1,000 over $25,000 (to $50,000); $643.75 + $7/each $1,000 over $50,000 (to $100,000); $993.75 + $5.60/each $1,000 over $100,000 (to $500,000); $3,233.75 + $4.75/each $1,000 over $500,000 (to $1,000,000); $5,608.75 + $3.65/each $1,000 over $1,000,000
Minimum Building Permit$60.60 ($60 permit + $0.60 state surcharge)
Plan Check65% of building permit fee
State Surcharge (D.O.C.)1% of building permit fee

Review timeline

~1021 business days

Typical estimate — confirm current times with the St. George building department

Inspection process

  1. 1

    Foundation

    Before concrete pour — forms, rebar, anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for occupancy

Tips

Frequently asked questions

How much does a residential building permit cost in St. George?
St. George City building permit fees follow the 1997 Uniform Building Code fee scale: $23.50 (up to $500), scaling to $5,608.75 + $3.65/each $1,000 over $1M. The minimum building permit is $60.60. Plan check is 65% of the permit fee. A 1% state surcharge (D.O.C.) applies. Mobile homes and swimming pools are each $200.
How long does permit review take in St. George?
St. George does not publish a fixed plan-review turnaround. Across Utah jurisdictions, residential plan review typically runs about 2-4 weeks, but times vary with project scope and department workload — confirm current timelines with the St. George building department before you submit.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-06-27.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the St. George building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in St. George

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.