Roofing Permit in St. George, Utah

Required for roof replacement, re-roofing, and structural roof repairs in St. George. Permit fees are valuation-based per the 1997 UBC building permit fee schedule.

Verified 2026-07-23 · Source

When you need this permit

  • Complete roof replacement (tear-off and re-roof)
  • Overlay of new roofing over existing (St. George allows a maximum of two roofing layers; a full tear-off is required if two layers already exist)
  • Structural roof repairs or modifications
  • Changes to roofing material type

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Roofing PermitAssessed on project valuation per St. George's published 1997 UBC building permit fee schedule (sgcityutah.gov Building Fee Sheet PDF, re-fetched and confirmed live 2026-07-01) — no separate roofing-specific flat fee is published; the valuation table itself is the grounded fee. Minimum $60.60; plan check 65%; D.O.C. 1%
Valuation-based per the 1997 Uniform Building Code fee scale (based on total value of roofing work)
Minimum PermitSt. George Building Fee Sheet
$60.60
Reinspection FeeSt. George City Impact Fees document (effective 4/21/21)
$47.00 per hour (minimum one-half hour)

Review timeline

Plan reviewTypical estimate — confirm current times with the St. George building department
~1–3 business days

How long did your Roofing Permit permit actually take in St. George?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition and replace damaged decking before proceeding; inspector must see sheathing before underlayment is installed

  2. 2

    Final

    Completed roof — roofing material and flashing completed; no extra material on roof (per St. George Residential Final Inspection Checklist item 9)

See the full St. George inspection guide — scheduling & re-inspection fees →

Tips

  • Roofing permits in St. George are typically approved within 1–3 business days — often same-day for straightforward replacements.
  • St. George allows a maximum of two roofing layers — if two layers already exist, a full tear-off to the deck is required before re-roofing.
  • Schedule the deck inspection before installing underlayment — the inspector must see the sheathing condition.
  • Ice and water shield requirements: confirm valley, eave, and penetration requirements with the Building Department at (435) 627-4100.

Frequently asked questions

Yes. St. George requires a building permit for complete roof replacements and re-roofing projects. The fee is valuation-based using the 1997 UBC fee scale, with a minimum of $60.60. Apply via the CityInspect portal at stg.cityinspect.com.

In St. George, the published Roofing Permit is: Valuation-based per the 1997 Uniform Building Code fee scale (based on total value of roofing work). Additional published fees: Minimum Permit — $60.60; Reinspection Fee — $47.00 per hour (minimum one-half hour). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Roofing permits in St. George are typically approved within 1–3 business days. Contact the Building Department at (435) 627-4100 for current turnaround times.

You'll need: Permit Application (CityInspect). Depending on your project, St. George may also ask for: Contractor License; Manufacturer Specifications. See the required-documents checklist on this page for details on each.

St. George requires 2 inspection(s) for a roofing permit, in order: Deck / Substrate, Final. Schedule each through St. George Building Department ((435) 627-4100).

Apply through St. George Building Department at 61 S Main St, St. George, UT 84770. Phone: (435) 627-4100, email: building@sgcity.org. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://sgcityutah.gov/departments/community_development/building_department.php.

St. George, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026 (statute version headed 'Effective 7/1/2026 (Superseded 1/1/2027)', confirmed by direct fetch 2026-07-16). Supersedes the 2021 IBC, which governed through 6/30/2026.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle — remains 2021 and continues in force (confirmed by direct statute fetch 2026-07-16).; Appendix AQ of the 2021 International Residential Code — Utah Code § 15A-2-103(1)(c) (confirmed by direct statute fetch 2026-07-16).; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle — remains 2023 (confirmed by direct statute fetch 2026-07-16).; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). ONE statewide edition — the statute does not split residential vs. commercial IECC editions. Supersedes the 2021 IECC, which governed through 6/30/2026.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IEBC, which governed through 6/30/2026.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — Utah Code § 15A-2-103(1)(n); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 ISPSC, which governed through 6/30/2026.; NOTE (2026-07-16 corpus-staleness fix): This file previously stated the 2021 editions as current and only forecasted the 7/1/2026 flip; the effective date has now passed and the entries above have been corrected to state the 2024 editions (per §15A-2-103(1)(a)/(d)/(e)/(f)/(h)/(i)/(n)) as current, with the superseded 2021 editions preserved as historical context. IRC (2021) and NEC (2023) were NOT changed — verified unchanged directly against the live statute. The International Fire Code (IFC) is NOT adopted anywhere in Utah Code § 15A-2-103 — the statute has no IFC subsection; St. George's own building department page does not independently cite an IFC edition, so no IFC entry appears in this list.. Local amendments apply — see the St. George overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the St. George building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.