Skip to main content
PermitBase

Commercial Building Permit in St. George, Utah

Required for new commercial construction in St. George, regulated by the 2024 IBC (current statewide per Utah Code § 15A-2-103, effective 7/1/2026). St. George publishes a dedicated 'Commercial Plan Submittal Requirements' checklist distinct from its residential process, and calculates the fee from the same 1997 Uniform Building Code valuation-based Building Fee Sheet used for residential permits — Based on Valuation, Plan Check 65% of the building permit fee, and a 1% D.O.C. (state surcharge), with a $60.60 minimum permit fee.

Verified 2026-07-23 · Source

When you need this permit

  • New commercial construction regulated by the 2024 IBC (Utah Code § 15A-2-103(1)(a))
  • A complete permit application form — 'Plans will not be accepted for review' until all Commercial Plan Submittal Requirements checklist items are complete, per the city's own checklist
  • One copy of the soils investigation report
  • One copy of the structural calculations
  • One copy of the 'Statement of Special Inspection' prepared by the design professional (one paper and one electronic copy)
  • Energy analysis showing compliance with the International Energy Conservation Code (one paper and one electronic copy) — St. George's own checklist form cites the 2015 IECC edition, which is stale relative to the current statewide 2024 IECC (Utah Code § 15A-2-103(1)(h), effective 7/1/2026); the statute controls regardless of the checklist form's un-updated edition reference
  • Material Safety Data Sheets (MSDS) for flammable or combustible liquids or other hazardous materials, if requested
  • Fire sprinkler and fire alarm plans submitted separately to the St. George Fire Department for review and approval, where applicable
  • An electronic copy of all submitted documents once plans are accepted as complete

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation-based (1997 UBC scale)St. George Building Fee Sheet (sgcityutah.gov/Documents/Departments/Community%20Development/Building%20Department/buildingfeesheet.pdf), '1997 Uniform Building Code - Building Fee Scale' — the same table used for the Residential Building Permit entry in this file; the fee sheet does not publish a separate commercial valuation table. DRIFT FIX 2026-07-23: the $25,001–$50,000 tier is corrected to $391.25 (from a previously published $391.75) — see the matching fee entry and note on the Residential Building Permit entry above for the two-source discrepancy this resolves (Building Fee Sheet prints $391.75 with an internal $14.50 table-jump inconsistency; the newer Impact Fees document (4/21/21) prints the arithmetically consistent $391.25).
$1–$500: $23.50. $501–$2,000: $23.50 for the first $500 plus $3.05 per additional $100 or fraction, to and including $2,000. $2,001–$25,000: $69.25 for the first $2,000 plus $14.00 per additional $1,000 or fraction, to and including $25,000. $25,001–$50,000: $391.25 for the first $25,000 plus $10.10 per additional $1,000 or fraction. $50,001–$100,000: $643.75 for the first $50,000 plus $7.00 per additional $1,000 or fraction. $100,001–$500,000: $993.75 for the first $100,000 plus $5.60 per additional $1,000 or fraction. $500,001–$1,000,000: $3,233.75 for the first $500,000 plus $4.75 per additional $1,000 or fraction. $1,000,001 and up: $5,608.75 for the first $1,000,000 plus $3.65 per additional $1,000 or fraction.
Plan Check FeeSt. George Building Fee Sheet: 'Plan Check 65% (.65) of Building Permit.' Not split by residential vs. commercial.
65% (.65) of the Building Permit fee
State Permit Surcharge (D.O.C.)St. George Building Fee Sheet: 'Plus 1% D.O.C. (of building permit fee)' — listed under the Modular line but applied as the statewide Uniform Building Standard Act surcharge; minimum building permit is $60.60 ($60.00 Permit and $0.60 D.O.C.).
1% of the Building Permit fee
Habitat Control Plan FeeSt. George Building Fee Sheet: 'Habitat Control Plan .2% (.002) of Valuation.'
0.2% (.002) of Valuation

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in St. George?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Standard IBC inspection sequence before concrete pour.

  2. 2

    Structural / Framing

    Framing and structural elements, including fire barriers, fire walls, and fire-stopping, verified against submitted plans before close-in.

  3. 3

    Fire Sprinkler / Fire Alarm

    Fire sprinkler and fire alarm systems inspected under separate review and approval by the St. George Fire Department, where applicable.

  4. 4

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  5. 5

    Final

    All work complete before occupancy.

See the full St. George inspection guide — scheduling & re-inspection fees →

Tips

  • St. George's Commercial Plan Submittal Requirements checklist explicitly states 'Plans will not be accepted for review' until every checklist item is verified and the signed form is submitted with the plan set — incomplete submittals are turned away rather than accepted with a review note.
  • The city's own Commercial Plan Submittal Requirements form cites the 2015 IECC for energy-compliance analysis — this is stale; the current statewide-mandatory edition is the 2024 IECC under Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Confirm the current edition with Development Services before preparing an energy analysis.
  • Fire sprinkler and fire alarm plans must be submitted separately to the St. George Fire Department for review and approval — they are not reviewed as part of the standard Building Department plan review.
  • St. George uses the same 1997 UBC valuation-based fee scale, 65% Plan Check fee, and 1% D.O.C. surcharge for commercial permits as for residential — there is no separate commercial fee table.

Frequently asked questions

St. George requires a commercial building permit for: New commercial construction regulated by the 2024 IBC (Utah Code § 15A-2-103(1)(a)); A complete permit application form — 'Plans will not be accepted for review' until all Commercial Plan Submittal Requirements checklist items are complete, per the city's own checklist; One copy of the soils investigation report; One copy of the structural calculations; One copy of the 'Statement of Special Inspection' prepared by the design professional (one paper and one electronic copy); Energy analysis showing compliance with the International Energy Conservation Code (one paper and one electronic copy) — St. George's own checklist form cites the 2015 IECC edition, which is stale relative to the current statewide 2024 IECC (Utah Code § 15A-2-103(1)(h), effective 7/1/2026); the statute controls regardless of the checklist form's un-updated edition reference; Material Safety Data Sheets (MSDS) for flammable or combustible liquids or other hazardous materials, if requested; Fire sprinkler and fire alarm plans submitted separately to the St. George Fire Department for review and approval, where applicable; An electronic copy of all submitted documents once plans are accepted as complete. If your project isn't listed, confirm with St. George Building Department at (435) 627-4100 before starting work.

St. George uses the same 1997 UBC valuation-based fee scale as residential permits, plus a Plan Check fee of 65% of the building permit fee and a 1% D.O.C. state surcharge. The minimum building permit fee is $60.60. No separate commercial valuation table is published.

St. George does not publish a plan-review timeline for this permit. Contact St. George Building Department at (435) 627-4100 for current turnaround.

You'll need: Commercial Plan Submittal Requirements Checklist; Commercial - Contractors Statement of Responsibility; Building Permit Application (CityInspect). Depending on your project, St. George may also ask for: Commercial - Deferred Submittal Agreement. See the required-documents checklist on this page for details on each.

St. George requires 5 inspection(s) for a commercial building permit, in order: Foundation / Footing, Structural / Framing, Fire Sprinkler / Fire Alarm, MEP Rough-In, Final. Schedule each through St. George Building Department ((435) 627-4100).

Apply through St. George Building Department at 61 S Main St, St. George, UT 84770. Phone: (435) 627-4100, email: building@sgcity.org. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://sgcityutah.gov/departments/community_development/building_department.php.

St. George, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026 (statute version headed 'Effective 7/1/2026 (Superseded 1/1/2027)', confirmed by direct fetch 2026-07-16). Supersedes the 2021 IBC, which governed through 6/30/2026.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle — remains 2021 and continues in force (confirmed by direct statute fetch 2026-07-16).; Appendix AQ of the 2021 International Residential Code — Utah Code § 15A-2-103(1)(c) (confirmed by direct statute fetch 2026-07-16).; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle — remains 2023 (confirmed by direct statute fetch 2026-07-16).; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). ONE statewide edition — the statute does not split residential vs. commercial IECC editions. Supersedes the 2021 IECC, which governed through 6/30/2026.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IEBC, which governed through 6/30/2026.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — Utah Code § 15A-2-103(1)(n); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 ISPSC, which governed through 6/30/2026.; NOTE (2026-07-16 corpus-staleness fix): This file previously stated the 2021 editions as current and only forecasted the 7/1/2026 flip; the effective date has now passed and the entries above have been corrected to state the 2024 editions (per §15A-2-103(1)(a)/(d)/(e)/(f)/(h)/(i)/(n)) as current, with the superseded 2021 editions preserved as historical context. IRC (2021) and NEC (2023) were NOT changed — verified unchanged directly against the live statute. The International Fire Code (IFC) is NOT adopted anywhere in Utah Code § 15A-2-103 — the statute has no IFC subsection; St. George's own building department page does not independently cite an IFC edition, so no IFC entry appears in this list.. Local amendments apply — see the St. George overview page for the full list.

Per St. George's official Commercial Plan Submittal Requirements checklist, submittals require a complete permit application, soils investigation report, structural calculations, a design professional's Statement of Special Inspection, an energy analysis, MSDS for hazardous materials if requested, and a full plan set (site plan, code analysis summary, floor plans, elevations, sections, details, and electrical/plumbing/mechanical plans). Fire sprinkler and fire alarm plans are reviewed separately by the Fire Department. Plans are not accepted for review until the checklist is complete.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the St. George building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in St. George.