Commercial Building Permit in St. George, Utah
Required for new commercial construction in St. George, regulated by the 2024 IBC (current statewide per Utah Code § 15A-2-103, effective 7/1/2026). St. George publishes a dedicated 'Commercial Plan Submittal Requirements' checklist distinct from its residential process, and calculates the fee from the same 1997 Uniform Building Code valuation-based Building Fee Sheet used for residential permits — Based on Valuation, Plan Check 65% of the building permit fee, and a 1% D.O.C. (state surcharge), with a $60.60 minimum permit fee.
Verified 2026-07-23 · Source
When you need this permit
- New commercial construction regulated by the 2024 IBC (Utah Code § 15A-2-103(1)(a))
- A complete permit application form — 'Plans will not be accepted for review' until all Commercial Plan Submittal Requirements checklist items are complete, per the city's own checklist
- One copy of the soils investigation report
- One copy of the structural calculations
- One copy of the 'Statement of Special Inspection' prepared by the design professional (one paper and one electronic copy)
- Energy analysis showing compliance with the International Energy Conservation Code (one paper and one electronic copy) — St. George's own checklist form cites the 2015 IECC edition, which is stale relative to the current statewide 2024 IECC (Utah Code § 15A-2-103(1)(h), effective 7/1/2026); the statute controls regardless of the checklist form's un-updated edition reference
- Material Safety Data Sheets (MSDS) for flammable or combustible liquids or other hazardous materials, if requested
- Fire sprinkler and fire alarm plans submitted separately to the St. George Fire Department for review and approval, where applicable
- An electronic copy of all submitted documents once plans are accepted as complete
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Standard IBC inspection sequence before concrete pour.
- 2
Structural / Framing
Framing and structural elements, including fire barriers, fire walls, and fire-stopping, verified against submitted plans before close-in.
- 3
Fire Sprinkler / Fire Alarm
Fire sprinkler and fire alarm systems inspected under separate review and approval by the St. George Fire Department, where applicable.
- 4
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against submitted plans.
- 5
Final
All work complete before occupancy.
See the full St. George inspection guide — scheduling & re-inspection fees →
Tips
- St. George's Commercial Plan Submittal Requirements checklist explicitly states 'Plans will not be accepted for review' until every checklist item is verified and the signed form is submitted with the plan set — incomplete submittals are turned away rather than accepted with a review note.
- The city's own Commercial Plan Submittal Requirements form cites the 2015 IECC for energy-compliance analysis — this is stale; the current statewide-mandatory edition is the 2024 IECC under Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Confirm the current edition with Development Services before preparing an energy analysis.
- Fire sprinkler and fire alarm plans must be submitted separately to the St. George Fire Department for review and approval — they are not reviewed as part of the standard Building Department plan review.
- St. George uses the same 1997 UBC valuation-based fee scale, 65% Plan Check fee, and 1% D.O.C. surcharge for commercial permits as for residential — there is no separate commercial fee table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the St. George building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in St. George.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in St. George
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your St. George project checklist
Describe your project once and get every permit, document, and fee it triggers in St. George — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →