Residential Building Permit (New Custom Home) in Peoria, Arizona

Required for the construction of a new custom single-family residential home in Peoria. Plans are submitted online at the Peoria Development Services portal (devservices.peoriaaz.gov) along with a completed 400NR – New Custom Home Application. Submittals must include one complete set of 24" x 36" plans, site plan, lot grading plan, soils report, structural calculations, and truss calculations (if not Arizona registrant-designed). The City uses a 4-day work week (Mon–Thu) and all plan review timelines are in business days. A separate Fire Department review is also required for fire sprinkler systems.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building permit — valuation-based$0 value/minimum: $87; $1–$500: $87; $501–$2,000: $87 for first $500 + $3.05 per each additional $100 or fraction; $2,001–$25,000: $120.25 for first $2,000 + $14 per additional $1,000 or fraction; $25,001–$50,000: $443.25 for first $25,000 + $10.10 per additional $1,000 or fraction; $50,001–$100,000: $695.25 for first $50,000 + $7 per additional $1,000 or fraction; $100,001–$500,000: $1,045.25 for first $100,000 + $5.60 per additional $1,000 or fraction; $500,001–$1,000,000: $3,285.25 for first $500,000 + $4.75 per additional $1,000 or fraction; $1,000,001 and up: $5,660.25 for first $1,000,000 + $3.65 per additional $1,000 or fractionPeoria Development Fee Schedule, Rev. 9/2025. Valuation is based on the Peoria Building Valuation Table: single-family dwellings (V-B, 'Other' column) = $47.50/sq ft; private garage = $19.50/sq ft; open carport = $13/sq ft; covered patio/deck = $13/sq ft.
Plan check fee65% of the building permit feePeoria Development Fee Schedule, Rev. 9/2025. Plan check fee applies in addition to the permit fee.
Plot plan review$87 per permit (standard residential plot plan review)Peoria Development Fee Schedule, Rev. 9/2025 — 'Review of Standard Home Plot Plan: $87'. Applies where a plot plan review is required.
Re-inspection fee$230 per re-inspectionPeoria Development Fee Schedule, Rev. 9/2025 — 'Reinspection Fee: $230'.

Review timeline

1818 business days

Peoria’s published plan-review target

Inspection process

  1. 1

    Foundation / Stem Wall

    After foundation/footing excavation and forms placed, before concrete placement. Covers continuous footing size/depth, horizontal and vertical steel, concrete cover, UFER grounding, and stem wall details including anchor bolts, shear wall hold-downs, and masonry joints per the Residential Inspection Checklist (Handout 208).

  2. 2

    Underground Plumbing and Pre-Slab

    Before slab pour: underground sewer (material, slope, cleanouts), soils/water service lines (pressure tested at 50 psi minimum for 15 minutes), underground gas (sleeved and vented), and interior bearing footing reinforcing. Pre-slab items include aggregate base, slab thickness, and copper/plastic piping sleeves at IBFs.

  3. 3

    Roof Deck / Exterior Strap and Shear

    Roof deck nailing per plans (8d @ 6" OC edges, 12" OC field minimum); truss layout and design calcs on site; trusses match calcs for size, grade, and plate connectors; exterior shear wall transfer connections; attic venting installed per plans.

  4. 4

    Rough Framing (Strap & Shear) and Rough Trades

    After rough framing is complete: exterior studs, top plates, beams, shear panels, and hold-downs. Also covers rough plumbing, rough mechanical/HVAC, and rough electrical before insulation and drywall.

  5. 5

    Final

    After all construction is complete. Covers exterior completion (address numbers visible, all wall finishes/paint, roofing complete, vents installed, grade away from foundation), electric panel complete (UFER, bonds, breakers, labeling), all fixtures and equipment, smoke/CO detectors, fire sprinkler final (if required), water meter set, and engineering clearances. A final clearance tag is left on the electric service panel. Project is not considered complete until an approved final inspection is on record.

Tips

Frequently asked questions

Where do I submit a new custom home permit application in Peoria?
All plan submittals are made online at https://devservices.peoriaaz.gov. You will need a completed 400NR application and one set of 24" x 36" plans. The Building Development counter is at 9875 N. 85th Avenue and can be reached at 623-773-7225 or building.applications@peoriaaz.gov. Source: City of Peoria Custom Home Plan Submittal Guide (Handout 253).
How are building permit fees calculated in Peoria?
Fees are valuation-based using the Peoria Development Fee Schedule (Rev. 9/2025). First, determine the project valuation using the Peoria Building Valuation Table (e.g., single-family dwelling = $47.50/sq ft, private garage = $19.50/sq ft). Then apply the tiered permit fee to that valuation. The plan check fee is an additional 65% of the permit fee. Source: Peoria Development Fee Schedule, Rev. 9/2025.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Peoria building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Peoria

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.