EV Charger / EVSE Permit in Peoria, Arizona
The City of Peoria permits EV charger installations as electrical work via the 400M – Miscellaneous Building Permit Application (the same standalone-electrical mechanism used for service upgrades, subpanels, and solar de-rates), governed by the 2017 NEC as adopted with City amendments per Ordinance 2019-12. A secondary source (search-indexed content citing Peoria City Code Fee Table 27-6, Development and Engineering Department/Building Safety fees) reports a possible flat $45.00 fee category covering 'additions, alterations, remodeling, accessory structures, EV chargers, meter relocation and service replacement,' but this specific figure could not be independently confirmed against the primary source in this review — both codelibrary.amlegal.com (Cloudflare-blocked, HTTP 403) and the City's own live Development Fee Schedule PDF (also HTTP 403) refused automated access, and a repeat search did not reproduce the same figure. The independently verified fee mechanism is the City's general valuation-based Electrical Permit fee (minimum $87), documented in this file's electrical-permit entry from the same Development Fee Schedule (Rev. 9/2025).
Verified 2026-07-20 · Source
When you need this permit
- Electrical work for an EV charger must comply with the 2017 NEC as adopted and amended per Ordinance 2019-12
- Submit online at devservices.peoriaaz.gov with a 400M – Miscellaneous Building Permit Application for a standalone EV charger circuit; electrical work within a larger building permit uses that project's application instead
- Contractor information (name, Peoria Business License, AZROC number) required at permit issuance
- A possible dedicated flat fee for EV chargers is referenced in secondary sources citing Peoria City Code Fee Table 27-6, but was not independently confirmed against the primary source in this review — confirm current fee directly with Development Services before applying
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Electrical
EVSE installed and verified; exterior GFCI protection, proper breaker sizing, and equipment disconnects per NEC
See the full Peoria inspection guide — scheduling & re-inspection fees →
Tips
- Peoria processes EV charger installations through the 400M – Miscellaneous Building Permit Application, the same form used for service upgrades and solar panel de-rates.
- A possible dedicated $45 flat fee for EV chargers is referenced in secondary sources citing City Code Fee Table 27-6, but could not be confirmed directly against the primary source in this review due to access restrictions — confirm the current fee with Development Services before budgeting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Peoria building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Peoria
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →