Eloy is served by the independent Eloy Fire District (formed August 19, 1946, predating the City of Eloy's own incorporation; serves over 10,300 residents across 55+ square miles), which conducts its own plan review, permitting, invoicing, and inspections for fire protection systems directly through its Fire Marshal's office — a separate process from the City of Eloy Community Development Building Safety Division. A single 'Operational/Special Use Permit' application covers fire alarm systems and automatic fire sprinkler systems (along with kitchen hood suppression, standpipes, and other fire protection systems), but the Fire District publishes genuinely distinct fee line items for each: a flat fee for fire alarm systems and a plan-review-plus-head-count fee structure for sprinkler systems. Governed by the 2018 International Codes and referenced NFPA standards as adopted by the Eloy Fire District.

Verified 2026-07-23 · Source

When you need this permit

  • A dedicated Eloy Fire District permit (submitted to the Fire Marshal's office, separate from the City's iworq building-permit portal) is required before installing an automatic fire sprinkler system, a fire alarm system, a fire pump, standpipes, an automatic kitchen hood extinguishing system, or an above-ground fuel storage tank
  • Submit the Eloy Fire District permit application, a one-page site plan, and a complete set of plans/drawings to the Fire Marshal (520-466-3544) — either one electronic set of plans or two paper sets; re-submittals of approved plans should include the plan name or number
  • Commercial projects must include documentation for all required fire protection systems (sprinklers, standpipes, fire alarms, kitchen suppression) even if a system is deferred, including calculations and component cut sheets
  • All necessary Eloy Fire District permits must be obtained BEFORE commencing construction; starting work without the required permit results in doubled permit and review fees
  • A copy of the approved Eloy Fire District Permit is a required submittal item on the corresponding City of Eloy building permit application (confirmed on the City's 2018 IRC Minimum Submittal Checklist, Part III)
  • Permits expire if work does not begin within 180 days, or if work is suspended for 180 consecutive days; written extension requests are accepted
  • Ongoing fire & life safety system inspection/maintenance reports (for fire sprinkler systems, fire alarm systems, kitchen hood suppression, standpipes, fire pumps, and other tracked systems) must be submitted electronically via The Compliance Engine (contact Brycer, (630) 413-9511, for training/support)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire Alarm System (Construction Permit)Eloy Fire District Permit Fees (2024); includes system plans review and acceptance testing. Verified against both the Fire District's published fee schedule and its own Operational/Special Use Permit application form, which lists 'Fire Alarm' as a $250.00 line item.
$250.00
Automatic Fire Sprinkler System — Plan ReviewEloy Fire District Permit Fees (2024)
$100.00 per hour (2-hour minimum)
Automatic Fire Sprinkler System — Permit Fee, up to 100 headsEloy Fire District Permit Fees (2024)
$100.00
Automatic Fire Sprinkler System — Permit Fee, 101-500 headsEloy Fire District Permit Fees (2024); each additional 100 heads above 500 adds $100.00
$250.00
Automatic Hood Extinguishing System (Kitchen Suppression)Eloy Fire District Permit Fees (2024); includes system plans review and acceptance testing
$250.00
Site Plan Review (general, applies when required for the project)Eloy Fire District Permit Fees (2024); Access Roads review is included within this Site Plan Review fee
$100.00 per hour (2-hour minimum)
Late-permit penaltyEloy Fire District Permit Fees (2024) and Fire Permit and Compliance Guide — applies when construction begins before the required Fire District permit is obtained
Permit and review fees are doubled

Review timeline

Plan reviewEloy’s published plan-review target
14–14 business days

How long did your Fire Sprinkler & Fire Alarm Permit (Eloy Fire District) permit actually take in Eloy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Preliminary Plan Review

    Initial Fire District review of submitted plans/drawings

  2. 2

    Final Plan Review

    Final Fire District plan approval before permit issuance

  3. 3

    Inspection — Access

    Conducted prior to combustibles being allowed on the property

  4. 4

    Inspection — Construction

    In-progress construction inspection of the fire protection system

  5. 5

    Inspection — Final (Acceptance/Final Testing)

    Final acceptance testing of the installed fire alarm or fire sprinkler system; call the Fire District (520-466-3544) for inspection or reinspection

See the full Eloy inspection guide — scheduling & re-inspection fees →

Tips

  • Eloy Fire District is a genuinely separate special taxing district (formed 1946, predating the City's own incorporation) with its own Fire Marshal, its own permit application, and its own fee schedule — it is NOT a division of the City of Eloy Community Development Department, and its permits are not submitted through the City's iworq portal.
  • Fire Alarm and Automatic Fire Sprinkler System permits are both requested on the same Eloy Fire District 'Operational/Special Use Permit' form, but they carry genuinely distinct fee structures: Fire Alarm is a flat $250.00, while sprinkler systems are billed on an hourly plan-review rate plus a head-count-tiered permit fee — treat them as two line items on one application rather than two separate application processes.
  • Obtain the Fire District permit BEFORE starting construction — the Fire District's own fee schedule and compliance guide both state that starting work first doubles the permit and review fees.
  • A copy of the approved Eloy Fire District Permit must be included with the corresponding City of Eloy building permit submittal — the City's own 2018 IRC Minimum Submittal Checklist lists this as a required Part III item.

Frequently asked questions

Eloy requires a fire sprinkler & fire alarm permit (eloy fire district) for: A dedicated Eloy Fire District permit (submitted to the Fire Marshal's office, separate from the City's iworq building-permit portal) is required before installing an automatic fire sprinkler system, a fire alarm system, a fire pump, standpipes, an automatic kitchen hood extinguishing system, or an above-ground fuel storage tank; Submit the Eloy Fire District permit application, a one-page site plan, and a complete set of plans/drawings to the Fire Marshal (520-466-3544) — either one electronic set of plans or two paper sets; re-submittals of approved plans should include the plan name or number; Commercial projects must include documentation for all required fire protection systems (sprinklers, standpipes, fire alarms, kitchen suppression) even if a system is deferred, including calculations and component cut sheets; All necessary Eloy Fire District permits must be obtained BEFORE commencing construction; starting work without the required permit results in doubled permit and review fees; A copy of the approved Eloy Fire District Permit is a required submittal item on the corresponding City of Eloy building permit application (confirmed on the City's 2018 IRC Minimum Submittal Checklist, Part III); Permits expire if work does not begin within 180 days, or if work is suspended for 180 consecutive days; written extension requests are accepted; Ongoing fire & life safety system inspection/maintenance reports (for fire sprinkler systems, fire alarm systems, kitchen hood suppression, standpipes, fire pumps, and other tracked systems) must be submitted electronically via The Compliance Engine (contact Brycer, (630) 413-9511, for training/support). If your project isn't listed, confirm with City of Eloy Community Development Department — Building Safety Division at 520-466-2578 before starting work.

Plan review is $100.00 per hour (2-hour minimum), and the permit fee itself is $100.00 for systems up to 100 heads, $250.00 for 101-500 heads, and an additional $100.00 for each additional 100 heads beyond that, per the Eloy Fire District's 2024 Permit Fee schedule.

The Eloy Fire District's own Fire Permit and Compliance Guide states a typical turnaround of about 2 weeks for plan review, plus an additional 2 working days to issue the permit after payment.

You'll need: Eloy Fire District Operational/Special Use Permit Application; One-Page Site Plan; Complete Set of Plans/Drawings. See the required-documents checklist on this page for details on each.

Eloy requires 5 inspection(s) for a fire sprinkler & fire alarm permit (eloy fire district), in order: Preliminary Plan Review, Final Plan Review, Inspection — Access, Inspection — Construction, Inspection — Final (Acceptance/Final Testing). Schedule each through City of Eloy Community Development Department — Building Safety Division (520-466-2578).

Apply through City of Eloy Community Development Department — Building Safety Division at 595 N. C Street, Suite 102, Eloy, AZ 85131. Phone: 520-466-2578, email: Inspections@EloyAZ.gov. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Building/electrical/mechanical/plumbing permit applications and Right-of-Way/On-Site Civil Permit applications are submitted electronically through the City's iworq permit portal (eloypermits.portal.iworq.net); plan submittals must be PDF format, layers flattened, 50 MB maximum file size. Inspection Line: 520-464-3179. Permit Technicians: Chris Encisco (cencisco@eloyaz.gov), Nadine Diaz (ndiaz@eloyaz.gov).. Official information: https://eloyaz.gov/138/Building-Safety.

Eloy, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. § 9-802, adoption of public records/technical codes by reference). The City of Eloy independently adopts and administers its own construction codes through its Community Development Department / Building Safety Division under Chapter 5 (Building Regulations) of the Eloy City Code; it does not defer permitting to Pinal County. Source: City of Eloy Ordinance No. 20-900 (adopted December 14, 2020), adopting the City of Eloy Building Code pursuant to A.R.S. § 9-802; Eloy City Code § 5-3, Adoption of Codes.; 2018 International Building Code (IBC), as published by the International Code Council, adopted by reference with City of Eloy amendments (Eloy City Code § 5-3 and § 5-8, Amendments to the 2018 International Building Code). Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/22/2025-01/27/2025), Part II.; 2018 International Residential Code (IRC), as published by the International Code Council, adopted by reference with City of Eloy amendments (Eloy City Code § 5-9, Amendments to the 2018 International Residential Code). Governs one- and two-family dwelling construction. Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/22/2025-01/27/2025).; 2018 International Energy Conservation Code (IECC), adopted by reference with City of Eloy amendments; governs residential energy compliance (prescriptive, UA trade-off/RES-check, or performance path). Minimum HVAC efficiencies published by the Building Safety Division: 16 SEER minimum for air conditioning equipment (R403.3.1.2.1 amended, stricter than the unamended IECC baseline), 78% AFUE minimum for weatherized gas heating equipment and 80% AFUE for non-weatherized equipment. Source: City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/27/2025), Part II §§ X.g-X.h and XV.a.; 2018 International Existing Building Code (IEBC), adopted and amended by the Mayor and Council of the City of Eloy; applies to reconstruction, alteration, relocation, enlargement, replacement, repair, equipment, use/occupancy, and demolition of existing buildings or structures. Source: City of Eloy Ordinance No. 20-900.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference; swimming pool/spa barrier and enclosure/safety-device requirements administered consistent with Arizona Revised Statutes § 36-1681, as amended. Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 IRC Minimum Submittal Checklist, Part II § I.y.; 2018 International Fire Code (IFC), enforced by the Eloy Fire District for fire sprinkler and life-safety requirements; a copy of the approved Eloy Fire District Permit is a required submittal item for residential building permits. Source: City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/27/2025), Part III item 23.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference with City of Eloy amendments (note: electrical code cycle is one edition behind the 2018 ICC set). Source: City of Eloy Building Safety Division page (eloyaz.gov/138/Building-Safety); City of Eloy Ordinance No. 20-900.; City of Eloy Code, Chapter 5 (Building Regulations), including § 5-3 (Adoption of Codes), § 5-5 (Building Code Administration), § 5-8 (Amendments to the 2018 International Building Code), and § 5-9 (Amendments to the 2018 International Residential Code) — the operative local amendment layer over the adopted ICC model codes. Copies of all amendments are kept on file with the City Clerk and the Community Development Department. Source: Eloy, AZ Code of Ordinances (codelibrary.amlegal.com/codes/eloyaz).; Manufactured/factory-built homes and park models are regulated by the State of Arizona Department of Housing for construction/installation standards and licensing (permit fees for mobile homes are adopted from and updated annually by the State of Arizona Department of Housing); the City of Eloy separately charges local hook-up fees (sewer, water, electrical connections) for site placement. Source: City of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule (effective February 16, 2026), Mobile Home Licensing Fees and Mobile Home hook-up sections.. Local amendments apply — see the Eloy overview page for the full list.

The Eloy Fire District, an independent special taxing district formed in 1946 with its own Fire Marshal's office — not the City of Eloy Community Development Department. Applications, plan review, invoicing, and inspections for fire sprinkler and fire alarm systems all go through the Fire District directly (520-466-3544).