Demolition Permit in Eloy, Arizona

Required for demolition of residential and other structures in Eloy. Billed as a flat fee tiered by structure type (accessory/garage, single-family residence, or other), per the City's Consolidated Rate and Fee Schedule.

Verified 2026-07-07 · Source

When you need this permit

  • Building permit required before demolishing a structure within Eloy city limits
  • Fee is tiered by structure category: residential accessory building/garage, single-family residence, or structures other than residential single-family
  • Pinal County Dust Control Permit coordination expected given the City's location in the West Pinal Nonattainment Area
  • Project is not legally complete until an approved final inspection has occurred

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition of Buildings — Residential accessory building or garage, per structureCity of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule
$90.00
Demolition of Buildings — Single-family residence, per structureCity of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule
$90.00
Demolition of Buildings — Structures other than residential single-family, per structureCity of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule
$540.00

Review timeline

Plan reviewEloy’s published plan-review target
25–90 business days

How long did your Demolition Permit permit actually take in Eloy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verifies site condition and completion of demolition; the project is not legally complete without an approved final inspection

See the full Eloy inspection guide — scheduling & re-inspection fees →

Tips

  • The fee schedule lists demolition of a residential accessory building/garage and a single-family residence at the same $90.00 flat fee per structure, while non-single-family structures are billed at a much higher $540.00 per structure.
  • Demolition permits fall under the City's general 'Residential' A.R.S. § 9-835 timeframe absent a published dedicated demolition-specific track; coordinate a Pinal County Dust Control Permit before applying given Eloy's location in the West Pinal Nonattainment Area.

Frequently asked questions

Eloy requires a demolition permit for: Building permit required before demolishing a structure within Eloy city limits; Fee is tiered by structure category: residential accessory building/garage, single-family residence, or structures other than residential single-family; Pinal County Dust Control Permit coordination expected given the City's location in the West Pinal Nonattainment Area; Project is not legally complete until an approved final inspection has occurred. If your project isn't listed, confirm with City of Eloy Community Development Department — Building Safety Division at 520-466-2578 before starting work.

$90.00 per structure for a residential accessory building/garage or a single-family residence, or $540.00 per structure for other (non-single-family) structures, per the City of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule.

Eloy's published plan-review target for a demolition permit is 25–90 business days.

You'll need: City of Eloy Building Permit Application (Demolition); Site Plan. See the required-documents checklist on this page for details on each.

Eloy requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through City of Eloy Community Development Department — Building Safety Division (520-466-2578).

Apply through City of Eloy Community Development Department — Building Safety Division at 595 N. C Street, Suite 102, Eloy, AZ 85131. Phone: 520-466-2578, email: Inspections@EloyAZ.gov. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Building/electrical/mechanical/plumbing permit applications and Right-of-Way/On-Site Civil Permit applications are submitted electronically through the City's iworq permit portal (eloypermits.portal.iworq.net); plan submittals must be PDF format, layers flattened, 50 MB maximum file size. Inspection Line: 520-464-3179. Permit Technicians: Chris Encisco (cencisco@eloyaz.gov), Nadine Diaz (ndiaz@eloyaz.gov).. Official information: https://eloyaz.gov/138/Building-Safety.

Eloy, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. § 9-802, adoption of public records/technical codes by reference). The City of Eloy independently adopts and administers its own construction codes through its Community Development Department / Building Safety Division under Chapter 5 (Building Regulations) of the Eloy City Code; it does not defer permitting to Pinal County. Source: City of Eloy Ordinance No. 20-900 (adopted December 14, 2020), adopting the City of Eloy Building Code pursuant to A.R.S. § 9-802; Eloy City Code § 5-3, Adoption of Codes.; 2018 International Building Code (IBC), as published by the International Code Council, adopted by reference with City of Eloy amendments (Eloy City Code § 5-3 and § 5-8, Amendments to the 2018 International Building Code). Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/22/2025-01/27/2025), Part II.; 2018 International Residential Code (IRC), as published by the International Code Council, adopted by reference with City of Eloy amendments (Eloy City Code § 5-9, Amendments to the 2018 International Residential Code). Governs one- and two-family dwelling construction. Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/22/2025-01/27/2025).; 2018 International Energy Conservation Code (IECC), adopted by reference with City of Eloy amendments; governs residential energy compliance (prescriptive, UA trade-off/RES-check, or performance path). Minimum HVAC efficiencies published by the Building Safety Division: 16 SEER minimum for air conditioning equipment (R403.3.1.2.1 amended, stricter than the unamended IECC baseline), 78% AFUE minimum for weatherized gas heating equipment and 80% AFUE for non-weatherized equipment. Source: City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/27/2025), Part II §§ X.g-X.h and XV.a.; 2018 International Existing Building Code (IEBC), adopted and amended by the Mayor and Council of the City of Eloy; applies to reconstruction, alteration, relocation, enlargement, replacement, repair, equipment, use/occupancy, and demolition of existing buildings or structures. Source: City of Eloy Ordinance No. 20-900.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference; swimming pool/spa barrier and enclosure/safety-device requirements administered consistent with Arizona Revised Statutes § 36-1681, as amended. Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 IRC Minimum Submittal Checklist, Part II § I.y.; 2018 International Fire Code (IFC), enforced by the Eloy Fire District for fire sprinkler and life-safety requirements; a copy of the approved Eloy Fire District Permit is a required submittal item for residential building permits. Source: City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/27/2025), Part III item 23.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference with City of Eloy amendments (note: electrical code cycle is one edition behind the 2018 ICC set). Source: City of Eloy Building Safety Division page (eloyaz.gov/138/Building-Safety); City of Eloy Ordinance No. 20-900.; City of Eloy Code, Chapter 5 (Building Regulations), including § 5-3 (Adoption of Codes), § 5-5 (Building Code Administration), § 5-8 (Amendments to the 2018 International Building Code), and § 5-9 (Amendments to the 2018 International Residential Code) — the operative local amendment layer over the adopted ICC model codes. Copies of all amendments are kept on file with the City Clerk and the Community Development Department. Source: Eloy, AZ Code of Ordinances (codelibrary.amlegal.com/codes/eloyaz).; Manufactured/factory-built homes and park models are regulated by the State of Arizona Department of Housing for construction/installation standards and licensing (permit fees for mobile homes are adopted from and updated annually by the State of Arizona Department of Housing); the City of Eloy separately charges local hook-up fees (sewer, water, electrical connections) for site placement. Source: City of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule (effective February 16, 2026), Mobile Home Licensing Fees and Mobile Home hook-up sections.. Local amendments apply — see the Eloy overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.