Mechanical / HVAC Permit in Eloy, Arizona
Required for heating, ventilation, and air conditioning installations in Eloy, governed by the 2018 International Mechanical Code (IMC) as adopted by the City. New/replacement HVAC must meet the City's amended minimum efficiency thresholds (16 SEER, 78%/80% AFUE).
Verified 2026-07-07 · Source
When you need this permit
- Mechanical permit required for new heating/AC units, new locations or ductwork/curbing, fireplace inserts/replacement, firepits/BBQs/outdoor kitchens with gas connections, and new or replacement wall/ground-mounted equipment
- Governed by the 2018 IMC as adopted by the City of Eloy
- New and replacement HVAC equipment must be sized per ACCA Manual J, S, and D (load calculation, equipment selection, duct design); minimum 16 SEER for air conditioning equipment; minimum 78% AFUE (weatherized) / 80% AFUE (non-weatherized) for gas heating equipment
- New rooftop or attic-space units require a Roof System Confirmation (sealed engineer letter or truss manufacturer verification letter) and RESCheck for all new mechanical units
- Correct ROC license class must be listed for the specific mechanical work being performed Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Ductwork and equipment placement before walls closed
- 2
Final
Equipment operational, clearances and combustion air verified, efficiency ratings confirmed (16 SEER / 78-80% AFUE minimums)
See the full Eloy inspection guide — scheduling & re-inspection fees →
Tips
- Eloy's published minimum efficiency thresholds (16 SEER for AC, 78% AFUE weatherized / 80% AFUE non-weatherized gas heating) are stricter than the unamended 2018 IECC baseline — confirm equipment specs meet these before purchase.
- New rooftop or attic HVAC units require a Roof System Confirmation (sealed engineer letter or truss manufacturer letter) verifying the roof can support the new unit — this is commonly missed on straightforward change-outs that add curbing or relocate equipment.
- The 'HVAC Change-outs' fee already includes the plan review fee; ductwork replacement is billed as a separate additional line item ($180) on top of the unit change-out fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Eloy
Mechanical / HVAC Permit in other cities
Compare mechanical / hvac permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Eloy project checklist
Describe your project once and get every permit, document, and fee it triggers in Eloy — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →