Skip to main content
PermitBase

EV Charger / EVSE Permit (Dedicated Fee Category — Amount Unpublished) in Eloy, Arizona

Required for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Eloy, governed by the 2017 NEC (Article 625) as adopted by the City. Eloy is one of the few jurisdictions in this corpus with a NAMED, dedicated fee-schedule line item for EV chargers: 'Electrical Vehicle Charging Stations (Residential) - per station' appears as its own row in the City's Consolidated Rate and Fee Schedule, immediately alongside the dedicated Residential Photovoltaic Systems line items. However, unlike the PV rows (which carry published $60.00/$30.00 figures), the EV Charging Stations row's fee amount cell is genuinely BLANK/unpublished in both the January 12, 2026 and the February 16, 2026 amended versions of the schedule (independently checked both PDFs; identical blank cell in both). Separately, the City's own Minimal Electrical Only Permit Checklist (rev. 05/25/2026) explicitly lists 'EV charger' among the equipment types requiring Load Calculations under the general 'Adding Circuits or Outlets' electrical-permit submittal category, confirming EV chargers are permitted work but do not (yet) have a published dollar figure of their own. Re-chased 2026-07-20: downloaded the live PDF directly and rendered the exact table page (p.4 of the Amended Consolidated Rates and Fees, dated November 12, 2025) as an image for direct visual inspection (not just automated text extraction, which can misalign multi-column PDF tables) -- independently re-confirmed the 'Electrical Vehicle Charging Stations (Residential) -per station' row has a genuinely empty rate cell in both the FY 2025-2026 and Amended FY 2025-2026 columns, while every neighboring row (Photovoltaic, Demolition, Temporary Trailers, Generators, Mobile Home hook-up) carries a populated dollar figure. This is a confirmed, real gap in the City's own document, not an extraction artifact.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the EV charger circuit installation, filed via the City's iworq electronic permit portal
  • Load Calculations required for the EV charger circuit, per the City's Minimal Electrical Only Permit Checklist (rev. 05/25/2026), 'Adding Circuits or Outlets' section
  • Electrical schematic/floor plan showing new and existing circuit/outlet locations, circuit amperage, and GFCI/AFCI requirements
  • Correct ROC (Registrar of Contractors) license class must be listed for the electrical work being performed Contractor
  • Governed by the 2017 NEC as adopted by the City of Eloy, including Article 625 (Electric Vehicle Power Transfer System)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Vehicle Charging Stations (Residential) — per stationCity of Eloy Amended Consolidated Rate and Fee Schedule — this named line item appears in its own row (immediately adjacent to the Residential Photovoltaic Systems rows) in BOTH the January 12, 2026 and the February 16, 2026 amended versions of the schedule, but the dollar-amount cell for this specific row is empty in both, unlike every neighboring row. This is a genuine documented gap in the City's own published schedule, not an inferred or omitted figure by this corpus.
Not published (blank fee cell)
Issuance of each electrical permitCity of Eloy Amended Consolidated Rate and Fee Schedule, Electrical Permit Fees — the general issuance fee would apply in addition to whatever the (currently unpublished) EV-station fee turns out to be
$30.00 plus additional fee per item constructed/installed

Review timeline

Plan reviewEloy’s published plan-review target
25–90 business days

How long did your EV Charger / EVSE Permit (Dedicated Fee Category — Amount Unpublished) permit actually take in Eloy?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Charger circuit wiring and box placement before walls are closed, if applicable

  2. 2

    Final

    EVSE installed, GFCI/disconnect and connections verified per 2017 NEC Article 625

See the full Eloy inspection guide — scheduling & re-inspection fees →

Tips

  • Eloy is unusual among this corpus's jurisdictions in having created a NAMED 'Electrical Vehicle Charging Stations (Residential) - per station' fee-schedule row of its own — but the City has not yet published a dollar figure for it as of the February 16, 2026 amended schedule. Contact Community Development (520-466-2572) directly to confirm the current charge before applying, since the published schedule itself does not state one.
  • Independent of the missing fee figure, the City's own Minimal Electrical Only Permit Checklist explicitly names 'EV charger' as requiring Load Calculations under its general 'Adding Circuits or Outlets' electrical-permit category — so the permitting PROCESS itself is defined even though the specific FEE amount is not.
  • The $30.00 general electrical permit issuance fee (plus applicable unit fees for the underlying circuit/service work) would apply at minimum, on top of whatever the EV-station-specific charge turns out to be once published.

Frequently asked questions

Eloy requires an ev charger / evse permit (dedicated fee category — amount unpublished) for: Electrical permit required for the EV charger circuit installation, filed via the City's iworq electronic permit portal; Load Calculations required for the EV charger circuit, per the City's Minimal Electrical Only Permit Checklist (rev. 05/25/2026), 'Adding Circuits or Outlets' section; Electrical schematic/floor plan showing new and existing circuit/outlet locations, circuit amperage, and GFCI/AFCI requirements; Correct ROC (Registrar of Contractors) license class must be listed for the electrical work being performed; Governed by the 2017 NEC as adopted by the City of Eloy, including Article 625 (Electric Vehicle Power Transfer System). If your project isn't listed, confirm with City of Eloy Community Development Department — Building Safety Division at 520-466-2578 before starting work.

Eloy's own Amended Consolidated Rate and Fee Schedule has a dedicated line item titled 'Electrical Vehicle Charging Stations (Residential) - per station,' but the dollar amount for it is blank/unpublished in both the January and February 2026 versions of the schedule — a genuine gap in the City's own published document, not an inferred figure. Confirm the current charge directly with Community Development (520-466-2572) before applying; the general $30.00 electrical permit issuance fee applies at minimum.

Eloy's published plan-review target for an ev charger / evse permit (dedicated fee category — amount unpublished) is 25–90 business days.

You'll need: City of Eloy Building Permit Application (Electrical); Minimal Electrical Only Permit Checklist. See the required-documents checklist on this page for details on each.

Eloy requires 2 inspection(s) for an ev charger / evse permit (dedicated fee category — amount unpublished), in order: Rough-In, Final. Schedule each through City of Eloy Community Development Department — Building Safety Division (520-466-2578).

Apply through City of Eloy Community Development Department — Building Safety Division at 595 N. C Street, Suite 102, Eloy, AZ 85131. Phone: 520-466-2578, email: Inspections@EloyAZ.gov. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Building/electrical/mechanical/plumbing permit applications and Right-of-Way/On-Site Civil Permit applications are submitted electronically through the City's iworq permit portal (eloypermits.portal.iworq.net); plan submittals must be PDF format, layers flattened, 50 MB maximum file size. Inspection Line: 520-464-3179. Permit Technicians: Chris Encisco (cencisco@eloyaz.gov), Nadine Diaz (ndiaz@eloyaz.gov).. Official information: https://eloyaz.gov/138/Building-Safety.

Eloy, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. § 9-802, adoption of public records/technical codes by reference). The City of Eloy independently adopts and administers its own construction codes through its Community Development Department / Building Safety Division under Chapter 5 (Building Regulations) of the Eloy City Code; it does not defer permitting to Pinal County. Source: City of Eloy Ordinance No. 20-900 (adopted December 14, 2020), adopting the City of Eloy Building Code pursuant to A.R.S. § 9-802; Eloy City Code § 5-3, Adoption of Codes.; 2018 International Building Code (IBC), as published by the International Code Council, adopted by reference with City of Eloy amendments (Eloy City Code § 5-3 and § 5-8, Amendments to the 2018 International Building Code). Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/22/2025-01/27/2025), Part II.; 2018 International Residential Code (IRC), as published by the International Code Council, adopted by reference with City of Eloy amendments (Eloy City Code § 5-9, Amendments to the 2018 International Residential Code). Governs one- and two-family dwelling construction. Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/22/2025-01/27/2025).; 2018 International Energy Conservation Code (IECC), adopted by reference with City of Eloy amendments; governs residential energy compliance (prescriptive, UA trade-off/RES-check, or performance path). Minimum HVAC efficiencies published by the Building Safety Division: 16 SEER minimum for air conditioning equipment (R403.3.1.2.1 amended, stricter than the unamended IECC baseline), 78% AFUE minimum for weatherized gas heating equipment and 80% AFUE for non-weatherized equipment. Source: City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/27/2025), Part II §§ X.g-X.h and XV.a.; 2018 International Existing Building Code (IEBC), adopted and amended by the Mayor and Council of the City of Eloy; applies to reconstruction, alteration, relocation, enlargement, replacement, repair, equipment, use/occupancy, and demolition of existing buildings or structures. Source: City of Eloy Ordinance No. 20-900.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference; swimming pool/spa barrier and enclosure/safety-device requirements administered consistent with Arizona Revised Statutes § 36-1681, as amended. Source: City of Eloy Ordinance No. 20-900; City of Eloy 2018 IRC Minimum Submittal Checklist, Part II § I.y.; 2018 International Fire Code (IFC), enforced by the Eloy Fire District for fire sprinkler and life-safety requirements; a copy of the approved Eloy Fire District Permit is a required submittal item for residential building permits. Source: City of Eloy 2018 International Residential Code Minimum Submittal Checklist (rev. 01/27/2025), Part III item 23.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference with City of Eloy amendments (note: electrical code cycle is one edition behind the 2018 ICC set). Source: City of Eloy Building Safety Division page (eloyaz.gov/138/Building-Safety); City of Eloy Ordinance No. 20-900.; City of Eloy Code, Chapter 5 (Building Regulations), including § 5-3 (Adoption of Codes), § 5-5 (Building Code Administration), § 5-8 (Amendments to the 2018 International Building Code), and § 5-9 (Amendments to the 2018 International Residential Code) — the operative local amendment layer over the adopted ICC model codes. Copies of all amendments are kept on file with the City Clerk and the Community Development Department. Source: Eloy, AZ Code of Ordinances (codelibrary.amlegal.com/codes/eloyaz).; Manufactured/factory-built homes and park models are regulated by the State of Arizona Department of Housing for construction/installation standards and licensing (permit fees for mobile homes are adopted from and updated annually by the State of Arizona Department of Housing); the City of Eloy separately charges local hook-up fees (sewer, water, electrical connections) for site placement. Source: City of Eloy Amended 2025-2026 Consolidated Rate and Fee Schedule (effective February 16, 2026), Mobile Home Licensing Fees and Mobile Home hook-up sections.. Local amendments apply — see the Eloy overview page for the full list.

Yes. The City's Minimal Electrical Only Permit Checklist (rev. 05/25/2026) explicitly lists 'EV charger' among equipment types requiring Load Calculations under the 'Adding Circuits or Outlets' electrical-permit submittal category.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.