EV Charger / EVSE Permit (Dedicated Fee Category — Amount Unpublished) — Eloy, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://eloyaz.gov/DocumentCenter/View/9263/FY-2025---2026-Consolidated-Fee-Schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Dedicated Fee Category — Amount Unpublished) in Eloy, Arizona
Required for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Eloy, governed by the 2017 NEC (Article 625) as adopted by the City. Eloy is one of the few jurisdictions in this corpus with a NAMED, dedicated fee-schedule line item for EV chargers: 'Electrical Vehicle Charging Stations (Residential) - per station' appears as its own row in the City's Consolidated Rate and Fee Schedule, immediately alongside the dedicated Residential Photovoltaic Systems line items. However, unlike the PV rows (which carry published $60.00/$30.00 figures), the EV Charging Stations row's fee amount cell is genuinely BLANK/unpublished in both the January 12, 2026 and the February 16, 2026 amended versions of the schedule (independently checked both PDFs; identical blank cell in both). Separately, the City's own Minimal Electrical Only Permit Checklist (rev. 05/25/2026) explicitly lists 'EV charger' among the equipment types requiring Load Calculations under the general 'Adding Circuits or Outlets' electrical-permit submittal category, confirming EV chargers are permitted work but do not (yet) have a published dollar figure of their own. Re-chased 2026-07-20: downloaded the live PDF directly and rendered the exact table page (p.4 of the Amended Consolidated Rates and Fees, dated November 12, 2025) as an image for direct visual inspection (not just automated text extraction, which can misalign multi-column PDF tables) -- independently re-confirmed the 'Electrical Vehicle Charging Stations (Residential) -per station' row has a genuinely empty rate cell in both the FY 2025-2026 and Amended FY 2025-2026 columns, while every neighboring row (Photovoltaic, Demolition, Temporary Trailers, Generators, Mobile Home hook-up) carries a populated dollar figure. This is a confirmed, real gap in the City's own document, not an extraction artifact.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the EV charger circuit installation, filed via the City's iworq electronic permit portal
- Load Calculations required for the EV charger circuit, per the City's Minimal Electrical Only Permit Checklist (rev. 05/25/2026), 'Adding Circuits or Outlets' section
- Electrical schematic/floor plan showing new and existing circuit/outlet locations, circuit amperage, and GFCI/AFCI requirements
- Correct ROC (Registrar of Contractors) license class must be listed for the electrical work being performed Contractor
- Governed by the 2017 NEC as adopted by the City of Eloy, including Article 625 (Electric Vehicle Power Transfer System)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Charger circuit wiring and box placement before walls are closed, if applicable
- 2
Final
EVSE installed, GFCI/disconnect and connections verified per 2017 NEC Article 625
See the full Eloy inspection guide — scheduling & re-inspection fees →
Tips
- Eloy is unusual among this corpus's jurisdictions in having created a NAMED 'Electrical Vehicle Charging Stations (Residential) - per station' fee-schedule row of its own — but the City has not yet published a dollar figure for it as of the February 16, 2026 amended schedule. Contact Community Development (520-466-2572) directly to confirm the current charge before applying, since the published schedule itself does not state one.
- Independent of the missing fee figure, the City's own Minimal Electrical Only Permit Checklist explicitly names 'EV charger' as requiring Load Calculations under its general 'Adding Circuits or Outlets' electrical-permit category — so the permitting PROCESS itself is defined even though the specific FEE amount is not.
- The $30.00 general electrical permit issuance fee (plus applicable unit fees for the underlying circuit/service work) would apply at minimum, on top of whatever the EV-station-specific charge turns out to be once published.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Eloy
EV Charger / EVSE Permit (Dedicated Fee Category — Amount Unpublished) in other cities
Compare ev charger / evse permit (dedicated fee category — amount unpublished) fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Eloy project checklist
Describe your project once and get every permit, document, and fee it triggers in Eloy — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →