Commercial Building Permit — Eloy, Arizona · Requirements sheet
Verified 2026-07-29 · Source: https://eloyaz.gov/343/Building-Permits-checklists-and-forms
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Eloy, Arizona
Required for new commercial/industrial construction, building shells, additions, alterations, and tenant improvements to non-residential occupancies in the City of Eloy. Reviewed against the 2018 IBC (and applicable 2018 IFC, 2018 IECC, and 2017 NEC provisions) as adopted and amended under Chapter 5 of the Eloy City Code (Ordinance No. 20-900). There is no separate tenant-improvement permit type or checklist published by the City: TI work uses the same 'COMMERCIAL/INDUSTRIAL' project-type option on the standard City of Eloy Building Permit Application and the same valuation-based fee table as new commercial construction; the only TI-specific line item found is a distinct, lower Certificate of Occupancy fee.
Verified 2026-07-29 · Source
When you need this permit
- Building permit required for new commercial/industrial construction, building shells, additions, alterations, and tenant improvements to non-residential occupancies within Eloy city limits
- Selected via the 'COMMERCIAL/INDUSTRIAL' project-type checkbox on the City's standard Building Permit Application (rev. 07/14/2025, agent-authorization portion rev. 08/05/2025) — the same application form used for residential, solar, and all other project types, with fields for Occupancy Type, Construction Type/Classification, square footage, Fire District Permit #, and estimated construction value
- Plans must comply with the 2018 IBC/IFC/IECC and City of Eloy amendments; construction documents must be submitted as flattened PDFs (50 MB max per file) through the City's iworq electronic permit portal per the City's Electronic File Submittal Requirements
- Building Shell Permits are valued at 80% of the ICC Building Valuation Table (or signed construction contract cost, whichever is less); foundation-only permits are valued at 25% of the ICC table (or contract cost, whichever is less)
- A Fire District Permit is a required field/attachment on the Building Permit Application, and fire/life-safety systems (fire alarms, sprinklers, exit signage, exit hardware, fire extinguishers where required) must be installed and operative before occupancy
- Outdoor Lighting Compliance Worksheet required for multi-family and non-residential land uses (fully shielded fixtures per City Code § 21-4-5)
- Tenant improvement work to an existing non-residential building is not a distinct permit type in the City's published checklists or fee schedule — it is processed as a Commercial/Industrial building permit using the same valuation-based fee table; the only tenant-improvement-specific fee found is the Certificate of Occupancy line (see fees)
- A Certificate of Occupancy (separate permit-type entry in this dataset) requires sign-off from the City Engineer, Planning/Zoning, the Eloy Fire District, Water/Sewer, and the Water Department before the Building Inspector and Chief Building Official can issue it; occupancy or use of the structure prior to issuance is prohibited
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing and connections per 2018 IBC
- 3
Rough Mechanical/Electrical/Plumbing
Ductwork, wiring, and piping inspected before concealment
- 4
Fire/Life-Safety
Fire alarm, sprinkler, exit signage, and exit hardware systems verified operative before occupancy; coordinated with the Eloy Fire District
- 5
Final / Certificate of Occupancy
Requires sign-off from the City Engineer, Planning/Zoning, Eloy Fire District, Water/Sewer, and Water Department before the Building Inspector and Chief Building Official can issue the Certificate of Occupancy — see the separate Certificate of Occupancy / Change of Occupancy permit-type entry for the full sequence
See the full Eloy inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'tenant improvement permit' type in Eloy's published checklists, applications, or fee schedule — TI work to an existing non-residential building uses the same Commercial/Industrial building permit application and the same valuation-based fee table as new commercial construction. The only TI-specific figure found is a $30.00 Certificate of Occupancy fee per tenant improvement, versus $60.00 per building for new non-residential construction.
- Non-Residential/Subdivision permits carry a longer A.R.S. § 9-835 review timeframe than residential — 35 staff review days Administrative (Completeness) Review plus 95 staff review days Substantive Review (130 total), versus 90 total for Residential.
- Minor plan revisions after permit issuance cost more and require a longer minimum for commercial work: $270.00/hour with a 2-hour minimum, versus $135.00/hour with a 1-hour minimum for residential.
- A Building Shell Permit is valued at only 80% of the ICC Building Valuation Table (or contract cost if less) — confirm with Building Safety whether your project qualifies as a 'shell' before assuming the full valuation table applies.
- Budget separately for the Certificate of Occupancy step: it requires five different department sign-offs (City Engineer, Planning/Zoning, Fire District, Water/Sewer, Water Dept.) before the Building Inspector can even conduct the final inspection, none of which are captured in the 35/95-day plan-review timeframe above.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Eloy.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Eloy
Commercial Building Permit in other cities
Compare commercial building permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Eloy project checklist
Describe your project once and get every permit, document, and fee it triggers in Eloy — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →