Residential Addition / Remodel Permit — Eloy, Arizona · Requirements sheet
Verified 2026-07-07 · Source: https://eloyaz.gov/343/Building-Permits-checklists-and-forms
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Remodel Permit in Eloy, Arizona
Required for room additions, remodels, and alterations to existing one- and two-family dwellings in Eloy. Reviewed against the 2018 IRC as adopted and amended by the City, using the dedicated Residential Addition or Remodel Minimum Submittal Checklist.
Verified 2026-07-07 · Source
When you need this permit
- Building permit required for room additions, remodels, and alterations to existing single- and two-family residences
- Detached accessory structures 200 sq ft or less with no electrical, plumbing, or mechanical connections do not require a building permit, but Planning and Zoning approval of location is still required
- Cover sheet, site plan, and construction plans (floor plan, foundation plan, framing/deck plan, cross-section, elevations, energy code compliance, electrical/mechanical/plumbing plans as applicable) required per the Residential Addition or Remodel checklist
- Structural plan and calculations, truss calculations/layout, soils report, ResCheck, and Manual J/S/D load calculations required based on project scope
- Demolition plans required separately from new-construction plans when the scope includes demolition; existing, new, and remodeled areas must be clearly identified on the plans
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to the existing structure
- 3
Final
Completed work verified against approved plans
See the full Eloy inspection guide — scheduling & re-inspection fees →
Tips
- Residential additions/remodels fall under the City's general 'Residential' A.R.S. § 9-835 timeframe (25 administrative + 65 substantive staff review days = 90 overall) — the same track as new construction, since the fee schedule and checklists do not publish a separate faster timeframe specific to additions.
- Detached accessory structures 200 sq ft or less with no utility connections skip the building permit, but Planning and Zoning approval on siting is still required.
- Plan review fees for interior alterations, small detached accessory structures, patio covers, and gazebos on existing R-3 buildings are capped at $35.00, distinct from the uncapped 65%-of-permit-fee plan review on full new construction.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eloy building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Eloy
Residential Addition / Remodel Permit in other cities
Compare residential addition / remodel permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Eloy project checklist
Describe your project once and get every permit, document, and fee it triggers in Eloy — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →