Residential Building Permit (New Construction — SFR) in Florence, Arizona
Required for new single-family residential (SFR) construction in the Town of Florence, reviewed against the 2018 IRC and Town of Florence amendments. The Town's Building Permit Application distinguishes 'New Build / SFR - Standard Plan' from 'New Build / SFR - Non-Standard Plan' and 'New Build / MFR (Multi-Family Residential).' Applications are submitted via the SmartGov online Residential Permitting Portal or in person/email for commercial-track submittals.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new single-family and multi-family residential construction within Florence town limits
- Plans must comply with the 2018 IRC and Town of Florence amendments, including Climatic and Geographic Design Criteria (115 mph wind, Exposure C; Seismic Design Category B; 32°F winter design temperature; moderate-to-heavy termite potential; mandatory cooling to 80°F max)
- Termite pretreatment certification required for slab foundations (licensed applicator, Arizona Pest Control Commission rules)
- Submittal via the SmartGov Residential Permitting Portal (twn-florence-az.smartgovcommunity.com) using an applicant/company or homeowner access code, or by email to TOFPermits@FlorenceAZ.gov for commercial submittals
- Required attachments: Permit Application, Inspector Rights and Responsibilities acknowledgment, Owner Authorization Form or Owner Builder Affidavit, Licensed Contractor Written Estimate, Site Plan (property lines, setbacks, structures, streets, north arrow, utilities), Construction/Building Plans — combined into a single PDF Owner-builderContractor
- Plan review fee must be paid in full before review commences
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour; termite pretreatment certification verified
- 2
Framing
Structural framing, connections, egress, per 2018 IRC and Town of Florence Design Criteria
- 3
Final / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy issued ($75 fee)
See the full Florence inspection guide — scheduling & re-inspection fees →
Tips
- Per the Town of Florence Submittal Review Timelines document (published by Community Development, 224 W 20th St), a new-construction Residential submittal (which the chart also groups with accessory buildings, plumbing, electrical, mechanical, manufactured homes, park models, pools, remodel, solar, and gas) is allotted 20 business days for 1st and 2nd review, 15 business days for subsequent reviews — plus a 10-business-day Administrative (completeness) Review that runs in addition to the formal review. The 20-35 day range reflects the Administrative Review (10 days) plus 1st/2nd formal review (20 days) as the realistic total for a first-time submittal.
- Review times are business days only, excluding holidays, weekends, and any time plans are out for applicant revision; timeframes are not all-inclusive and can be adjusted by written agreement between the Town and applicant.
- 'Commercial New Construction — Single family residential home, standard plans, garage' also carries a 20-day (1st/2nd)/15-day (subsequent) review timeframe on the same chart, distinct from the 'Residential New Construction' row — both apply the same 20/15 review windows.
- Work commenced before permit issuance triggers a penalty fee equal to (per the Fee Schedule) 100% of the calculated permit fee, in addition to required fees.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Florence building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Florence
Residential Building Permit (New Construction — SFR) in other cities
Compare residential building permit (new construction — sfr) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Florence project checklist
Describe your project once and get every permit, document, and fee it triggers in Florence — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →