EV Charger / Electric Vehicle Charging Station Permit — Florence, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.florenceaz.gov/wp-content/uploads/documents/Community%20Development/Applications/PermitApplication/Packet%20-%20Mechanical,%20Plumbing,%20Electrical%20Application%20Rev%209.11.25.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit in Florence, Arizona
Florence has no dedicated EV charger permit — installation of an electric vehicle charging station (Level 1/2 EVSE) is electrical work and is processed under the same combined MPEW (Mechanical/Plumbing/Electrical/Walls-fences) and Inspection Permit Application used for the electrical-permit entry, billed at the Town's flat Utility Permit fee (Electrical category). No distinct EV-specific fee line appears in the Town's Fee Schedule, whose current figures for the Utility Permit (Electrical) are $75.00 residential / $300.00 commercial.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the EV charger circuit installation (new wiring, dedicated circuit, or panel/service work), same as any other electrical work
- Applied for on the combined MPEW / Inspection Permit Application (Rev 9.11.25), selecting 'Electrical' as Permit Type
- Governed by the National Electrical Code as adopted by the Town (see electrical-permit entry for edition-year notes)
- Apply via the SmartGov Residential Permitting Portal or email TOFPermits@FlorenceAZ.gov for commercial
- Arizona's statewide solar/PV statute (A.R.S. § 9-468) does not itself address EV charger permitting specifically, but Florence's general electrical permit fee-caps and process apply the same way to EV circuits as to any other electrical scope
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
EV charger equipment installed and tested; electrical bonding/grounding verified
See the full Florence inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'EV charger permit' in Florence — apply for the standard Electrical Permit (Utility Permit category) using the combined MPEW application.
- A simple utility clearance/EV circuit is processed over the counter with no formal review when complete; work requiring fuller plan review falls under the Town's 'Residential' review category (10-day Administrative Review plus 20 business days for 1st/2nd review), matching the electrical-permit entry's timeline.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Florence building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Florence's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Florence yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Florence lands. Privacy.
Other permits in Florence
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Arizona →
Look up this fee in a different city →