Commercial Building Permit — Florence, Arizona · Requirements sheet
Verified 2026-07-29 · Source: https://www.florenceaz.gov/wp-content/uploads/documents/Community%20Development/Applications/PermitApplication/Packet%20-%20Building%20Permit%20Application%20Rev%209.11.25.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Florence, Arizona
Required for new commercial construction and for interior/exterior alterations to existing commercial buildings in Florence, reviewed against the 2018 IBC and Town of Florence amendments plus ICC A117.1 (2010) accessibility standards. Tenant improvement work is folded into this same process rather than being a separate permit type: the Town's single Building Permit Application (Rev 9.11.25) has a 'COMMERCIAL' section with distinct 'New Build' and 'Tenant Improvement' checkboxes, but both are billed identically (Based-on-Valuation Building Permit Fee plus 65% plan review) and reviewed on the same track. The Town's own Submittal Review Timelines chart does list 'Commercial Tenant Improvement' and 'Commercial New Construction' as two separately named rows, but assigns them the identical review window.
Verified 2026-07-29 · Source
When you need this permit
- Building permit required for new commercial building construction ('New Build' checkbox) and for changes, alterations, upgrades, and repairs to the interior or exterior of a commercial building ('Tenant Improvement' checkbox) — both on the COMMERCIAL section of the same Building Permit Application (Rev 9.11.25)
- Per the Town's own Project Assessment/Commercial Site Inspection packet: 'Changes, alterations, upgrades, and repairs to the interior or exterior of a commercial building will require an application for a building permit... Permit fees are based on the valuation of the work performed' — confirming tenant improvement work uses the standard valuation-based Building Permit Fee, not a separate fee schedule
- Reviewed against the 2018 IBC (Town of Florence Code of Ordinances § 150.300(A)(1)) and Town amendments, plus ICC A117.1, 2010 Edition (§ 150.300(A)(12)), adopted in its entirety without revision
- Commercial-specific application fields (distinct from the Residential section of the same form): Sq Ft (Existing), Sq Ft (Added), Fire Sprinklers (Yes/No), Type of Construction, Existing Use, New Use, and Valuation
- Commercial submittals are emailed to TOFPermits@FlorenceAZ.gov (the SmartGov online portal is for Residential submittals only) or delivered in person (no rolled plans; 1-sided 8.5x11 paper only)
- The Town's Submittal Review Timelines chart caps its standard 20/15-business-day 'Commercial New Construction' track at 'Construction of a new commercial building under 50K SF, solar farms under 20MW' — the chart does not specify a distinct track for buildings at or above that threshold, and per the chart's own footnote, these timeframes 'do not apply to submittals that require approval through the Planning and Zoning Commission and/or Town Council'
- An optional, no-fee Project Assessment meeting (Zoning, Building Safety, Fire Safety, and Engineering/Public Works staff) can be requested before formal submittal, scheduled on a Thursday at least 5 business days after the request; findings are valid for 6 months
- An optional, no-fee, one-time Commercial Site Inspection (Building Safety Division and Fire Marshal) can be requested via the Building Permit Application, scheduled within 5 business days after the Project Assessment meeting, to provide a general code-deficiency walkthrough before formal submittal
- A Certificate of Occupancy, requiring sign-off from both the Building Safety Division and the Fire Department, is required before the building may be occupied
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Commercial Site Inspection (optional, pre-submittal)
One-time walkthrough by Building Safety and the Fire Marshal, available on request before formal submittal, to flag general code deficiencies
- 2
Rough-In (Structural / MEP)
Framing, structural connections, and mechanical/electrical/plumbing rough-in verified before concealment, per 2018 IBC and Town of Florence amendments
- 3
Final / Certificate of Occupancy
All work complete per approved plans; requires sign-off from both the Building Safety Division and the Fire Department before a Certificate of Occupancy is issued
See the full Florence inspection guide — scheduling & re-inspection fees →
Tips
- Tenant improvement work does not require a separate application or fee schedule from new commercial construction — both are scopes on the same Building Permit Application (Rev 9.11.25), COMMERCIAL section, billed the same Based-on-Valuation fee.
- The Submittal Review Timelines chart nonetheless names 'Commercial Tenant Improvement' ('Improvements to an existing building (shell), plumbing, electrical, mechanical, signs, fire sprinkler, fire alarm, hood system') and 'Commercial New Construction' ('Construction of a new commercial building under 50K SF, solar farms under 20MW') as two distinct rows — both carry the identical 20-business-day (1st/2nd review) / 15-business-day (subsequent review) window, plus the Town-wide 10-business-day Administrative (completeness) Review, for a realistic 20-35 business day range.
- Consider requesting the free, optional Project Assessment meeting (Zoning, Building Safety, Fire Safety, Engineering/Public Works) before submitting — it surfaces general requirements up front and its findings are valid for 6 months. A follow-on, also-free, one-time Commercial Site Inspection can then flag code deficiencies before formal plan review begins.
- Commercial Permit Revision Fee is $150 (versus $75 for Residential) per the Fee Schedule's Administrative Fees table.
- Certificate of Occupancy fee is inconsistent across the Town's own documents ($75 per the Town-wide Fee Schedule vs. $50 per the Community Development Department's Project Assessment/Commercial Site Inspection packet, which also states no additional C of O fee applies if a tenant-improvement permit was applied for) — confirm the exact figure with Community Development before budgeting.
- The 'under 50K SF' qualifier on the Commercial New Construction review-timeline row is not explained further in the Town's published documents — no separate review track for larger buildings was found; verify timing directly with the Building Official for any project at or above 50,000 square feet.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Florence building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Florence.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Florence
Commercial Building Permit in other cities
Compare commercial building permit fees across Arizona →
Look up this fee in a different city →