Demolition Permit in Somerton, Arizona
Required for demolition of any structure in the City of Somerton, using the City's dedicated Demolition Building Application. A flat fee applies and the City requires two inspections for demolition permits.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required before demolishing any structure within Somerton city limits
- Application must indicate number of buildings and housing units affected
- Building Application Form ('Other: Demolition' checked) plus Building Contractor's Information page required
- Two inspections are required for demolition permits per the City's fee schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition/Utility Disconnect Inspection
Verifies utilities have been properly terminated before demolition begins
- 2
Final Demolition Inspection
Confirms complete removal of structure and site clearance; two inspections are required per Resolution No. 2026-004
See the full Somerton inspection guide — scheduling & re-inspection fees →
Tips
- Per the City's A.R.S. § 9-835 Building Permit Processing Time Frames document, 'Residential Building – Demolition' carries a 1-business-day Administrative Completeness Review, 5 business days for 1st review, and 5 business days for 2nd review (if needed), for an overall review time of 11 business days; 'Commercial Building – Demolition' is 1/5/5 = 11 business days as well.
- The $50 demolition permit fee explicitly requires two inspections, per Resolution No. 2026-004 — budget for both to be scheduled.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Somerton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Somerton
Demolition Permit in other cities
Compare demolition permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Somerton project checklist
Describe your project once and get every permit, document, and fee it triggers in Somerton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →