Residential Building Permit (New Construction / Addition) — Burlington, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://burlingtoncolo.com/DocumentCenter/View/187/Building-Permit-Application-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction / Addition) in Burlington, Colorado
Required for new construction or additions to residential (and other) structures within Burlington city limits. Issued through City Hall on a single combined 'Building Permit Application / Zoning Compliance Application' form. Because Burlington has not adopted a local building code, the applicant is contractually bound (via the permit application itself) to follow applicable State of Colorado building-code guidance and any Colorado Department of Local Affairs/Division of Housing requirements rather than a codified local building code.
Verified 2026-07-06 · Source
When you need this permit
- Complete Part A (New Building, Addition, Garage, Fence, or Other) and Part C (Utility Taps) of the combined Building Permit/Zoning Compliance Application
- Attach a scale drawing of the tract and the building to be built, repaired, or altered, with utilities and sidewalks and all dimensions clearly indicated
- Attach a Title 17.12.030(B)-compliant zoning plat: scaled drawing showing exact lot shape/dimensions, exact size/location of existing and proposed buildings/structures and driveways, present and proposed use of the property, and location of all utility/service connections and drainage courses, plus relevant conditions within 15 feet of the lot perimeter
- Complete and return a separate Building Permit Locate Form: call 811 or 800-922-1987 for a utility line locate before construction begins (approximately 3-day turnaround, ticket valid 30 days, no charge unless lines must be moved); certify the structure is not built over a gas line or any utility line
- Sign the applicant certification acknowledging Burlington has not adopted a building code and that state building-code guidelines, local requirements, and DOLA/Division of Housing inspection requirements govern
- Employ only duly licensed plumbers and electricians for any plumbing/electrical work (Colorado state licensure, per State Plumbing Board/State Electrical Board) Contractor
- Disclose where construction materials will be purchased and pay the 2% city use tax on any materials purchased outside the city (Burlington Municipal Code Chapter 3.08), either by estimate at permit issuance or via affidavit if purchasing from an in-city licensed retailer
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Utility Locate Verification
811/800-922-1987 line-locate ticket must be completed and the Locate Form returned to City Hall before construction begins
- 2
Final/Field Inspection
Because no local building code is adopted and no dedicated Building Division/inspector is named in available City materials, Burlington does not publish a specific inspection sequence (e.g., foundation, framing, rough-in, final) for standard construction the way code-adopting jurisdictions in this corpus do. The permit form includes a 'Public Works' signoff line, indicating Public Works staff play some inspection/signoff role, but no itemized inspection checklist is published.
See the full Burlington inspection guide — scheduling & re-inspection fees →
Tips
- Burlington has NOT adopted a local building code — the permit application itself requires the owner to sign an acknowledgment of this fact and agree to follow state guidelines instead. Do not assume a specific IBC/IRC edition applies; confirm applicable state guidance directly with City Hall or the Colorado Division of Housing/OSA as relevant to your specific project type.
- Budget at least 3 business days for the mandatory utility line locate (811) before you can begin construction — the Locate Form must be returned to City Hall with your Building Permit Application, and structures cannot be built over any utility line including gas lines.
- If you plan to purchase construction materials from a retailer outside Burlington city limits, budget for the 2% municipal use tax (Chapter 3.08) — you can avoid the estimate-based method by filing an affidavit that all materials will be purchased from a licensed in-city retailer instead.
- The building permit fee schedule is valuation-based starting at a $25 minimum for very small projects, not a single flat fee — get a construction cost estimate before applying so City Hall can calculate your tier correctly.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Burlington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Burlington
Residential Building Permit (New Construction / Addition) in other cities
Compare residential building permit (new construction / addition) fees across Colorado →
Look up this fee in a different city →