EV Charger / EVSE Permit — South Salt Lake, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://sslc.gov/215/Building-Permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in South Salt Lake, Utah
South Salt Lake does not publish a distinct EV-charger/EVSE fee category. Installing electric vehicle charging equipment (EVSE) is electrical work and is processed through the same over-the-counter trade-permit path as other residential/commercial electrical work, billed under the applicable flat fee in the Consolidated Fee Schedule's electrical-service line items (e.g. Electrical Service Inside Upgrade / Electrical Service Upgrade 200A or less) rather than a standalone EV-specific charge. This is confirmed directly by South Salt Lake's own electrical-mechanical-plumbing-permit entry, which states EV charger/EVSE installation falls under this same trade-permit process and that the Consolidated Fee Schedule carries no distinct EV-charger line item (checked directly 2026-07-19).
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- New dedicated electrical circuit and/or electrical service/panel upgrade to serve the charger
- Compliance with the National Electrical Code as adopted by South Salt Lake Municipal Code § 8.10.080/8.10.020
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Final
Inspection of the new EVSE circuit and, if applicable, panel/service upgrade, by the Building Permits Division; scheduled at (801) 483-6032.
See the full South Salt Lake inspection guide — scheduling & re-inspection fees →
Tips
- South Salt Lake has no separate EV-charger fee category — file EV/EVSE installations as an electrical over-the-counter trade permit, billed at the applicable flat fee (e.g. $50.00 for an electrical service upgrade).
- If the installation requires a new or upgraded electrical service/panel, the same $50.00 Electrical Service Upgrade flat fee applies as for any other service change.
- Coordinate with the Building Permits Division at (801) 483-6063 ext. 2 if the scope is unclear, since South Salt Lake does not publish EV-specific guidance.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Salt Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in South Salt Lake
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your South Salt Lake project checklist
Describe your project once and get every permit, document, and fee it triggers in South Salt Lake — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →