Residential Building Permit (New Construction / Addition / Remodel) in South Salt Lake, Utah
Required for new single-family residential construction, additions, structural modifications, and most residential building system work in South Salt Lake. The Total Building Permit Fee is valuation-based, computed from current ICC Building Valuation Data (ICCBVD) per the city's own formula, rather than a flat table, per the official Consolidated Fee Schedule (last amended by Ord. No. 2025-17, 5-28-2025).
Verified 2026-07-23 · Source
When you need this permit
- New single-family residential construction, additions, or structural modifications to floor, walls, roof, windows, or doors
- Complete application submitted through the city's Building Permits process (220 E Morris Avenue, Suite 150)
- Compliance with the adopted 2012 IBC (with Appendix J amendment) / adopted IRC (with 2006 Appendix P) per Municipal Code § 8.10.010
- Plan Check Fee due at time of building permit application; Building Fee and State Surcharge Fee due prior to permit issuance
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Scheduled Building Inspections
Scheduled by calling (801) 483-6032, per the city's official Building Permits FAQ. All building permits require inspection; if work proceeds without a required inspection, uninspected components must be removed/replaced to confirm code compliance.
- 2
Certificate of Occupancy / Certificate of Completion
Issued by the Building Division once work is completed and found compliant with all applicable code requirements, per the official Building Permits page.
See the full South Salt Lake inspection guide — scheduling & re-inspection fees →
Tips
- South Salt Lake commits to reviewing all complete applications within 15 business days, with review comments sent by email to the application contact, per the city's official Building Permits page and FAQ.
- Permit applications are only valid for 180 days, per the official Building Permits page.
- Starting construction before permit approval can trigger a citation, a doubled application fee (100% of the Building Fee additional per the fee schedule), and potential criminal penalties for noncompliance.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Salt Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in South Salt Lake
Residential Building Permit (New Construction / Addition / Remodel) in other cities
Compare residential building permit (new construction / addition / remodel) fees across Utah →
Look up this fee in a different city →
Now live
Build your South Salt Lake project checklist
Describe your project once and get every permit, document, and fee it triggers in South Salt Lake — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →