Required for new single-family residential construction, additions, structural modifications, and most residential building system work in South Salt Lake. The Total Building Permit Fee is valuation-based, computed from current ICC Building Valuation Data (ICCBVD) per the city's own formula, rather than a flat table, per the official Consolidated Fee Schedule (last amended by Ord. No. 2025-17, 5-28-2025).

Verified 2026-07-23 · Source

When you need this permit

  • New single-family residential construction, additions, or structural modifications to floor, walls, roof, windows, or doors
  • Complete application submitted through the city's Building Permits process (220 E Morris Avenue, Suite 150)
  • Compliance with the adopted 2012 IBC (with Appendix J amendment) / adopted IRC (with 2006 Appendix P) per Municipal Code § 8.10.010
  • Plan Check Fee due at time of building permit application; Building Fee and State Surcharge Fee due prior to permit issuance

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (Building Fee + Plan Check Fee + State Surcharge Fee)South Salt Lake Consolidated Fee Schedule § 3.11.040.A (Ord. No. 2020-02, § V(Exh. D), 1-8-2020, as amended through Ord. No. 2025-17, § 1(Exh. A), 5-28-2025), confirmed via the city's official Municode-hosted code text. Valuation is based on the most current ICC Building Valuation Data, updated semi-annually; no fixed local multiplier value was published in the fee schedule text itself.
Building Fee (B) = local multiplier x Gross ICCBVD Valuation; Plan Check Fee (P) = B x 0.65; State Surcharge Fee (Y) = B x 0.01; Total = B + P + Y
Additional Plan Review (beyond initial + 2 reviews)South Salt Lake Consolidated Fee Schedule § 3.11.040.A: Building/Plan Check Fees include an initial review plus two subsequent reviews at no charge; additional hourly fees beyond that are $56.00/hour.
$56.00/hour
Inspection Re-FeeSouth Salt Lake Consolidated Fee Schedule § 3.11.040.A.
$56.00
Commencing Construction Prior to Permit IssuanceSouth Salt Lake Consolidated Fee Schedule § 3.11.040.A.
Additional 100% of the Building Fee
Culinary Water Impact FeeSouth Salt Lake Consolidated Fee Schedule § 3.11.040.B, current through Ord. No. 2025-17 (5-28-2025) — re-fetched and confirmed verbatim against the live Municode page 2026-07-23 (figures unchanged; also matches the Other-meter-connection formula '(water consumption, gdp)/(1,364 gdp/ERU)*($6,345 per ERC)'). This fee derives from the city's June 2024 Drinking Water Impact Fee Facilities Plan/Impact Fee Analysis, codified via Ord. No. 2024-11 (7-31-2024); no newer culinary-water impact fee ordinance was found.
3/4" meter $6,345.00; 1" meter $6,345.00; 1.5" meter $12,690.00; 2" meter $20,304.00
Wastewater Impact Fee (Non-PID Members, per typical residential connection)South Salt Lake Consolidated Fee Schedule § 3.11.040.B — re-fetched and confirmed verbatim against the live Municode page 2026-07-23 (figures unchanged). This is the current text of § 3.11.040.B specifically as amended by Ordinance No. 2025-17, § 1(Exh. A), 5-28-2025 (which amended the wastewater collection system impact fee); no newer amending ordinance to this subsection was found. A separate lower PID-member total of $1,160.00 (Treatment + Planning only) applies to properties within the Central Valley Water Reclamation PID service boundary.
Collection $10,400.00 + Treatment $1,063.00 + Planning $97.00 = $11,560.00 total
Parks Impact FeeSouth Salt Lake Consolidated Fee Schedule § 3.11.040.B — re-fetched and confirmed verbatim against the live Municode page 2026-07-23 (figures unchanged).
Single-family $1,677.00/household; Multi-Family $1,608.00/household

Review timeline

Plan reviewSouth Salt Lake’s published plan-review target
15–15 business days

How long did your Residential Building Permit (New Construction / Addition / Remodel) permit actually take in South Salt Lake?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Scheduled Building Inspections

    Scheduled by calling (801) 483-6032, per the city's official Building Permits FAQ. All building permits require inspection; if work proceeds without a required inspection, uninspected components must be removed/replaced to confirm code compliance.

  2. 2

    Certificate of Occupancy / Certificate of Completion

    Issued by the Building Division once work is completed and found compliant with all applicable code requirements, per the official Building Permits page.

See the full South Salt Lake inspection guide — scheduling & re-inspection fees →

Tips

  • South Salt Lake commits to reviewing all complete applications within 15 business days, with review comments sent by email to the application contact, per the city's official Building Permits page and FAQ.
  • Permit applications are only valid for 180 days, per the official Building Permits page.
  • Starting construction before permit approval can trigger a citation, a doubled application fee (100% of the Building Fee additional per the fee schedule), and potential criminal penalties for noncompliance.

Frequently asked questions

South Salt Lake requires a residential building permit (new construction / addition / remodel) for: New single-family residential construction, additions, or structural modifications to floor, walls, roof, windows, or doors; Complete application submitted through the city's Building Permits process (220 E Morris Avenue, Suite 150); Compliance with the adopted 2012 IBC (with Appendix J amendment) / adopted IRC (with 2006 Appendix P) per Municipal Code § 8.10.010; Plan Check Fee due at time of building permit application; Building Fee and State Surcharge Fee due prior to permit issuance. If your project isn't listed, confirm with South Salt Lake Community Development Department, Building Permits Division at (801) 483-6063, ext. 2 before starting work.

In South Salt Lake, the published Building Permit Fee (Building Fee + Plan Check Fee + State Surcharge Fee) is: Building Fee (B) = local multiplier x Gross ICCBVD Valuation; Plan Check Fee (P) = B x 0.65; State Surcharge Fee (Y) = B x 0.01; Total = B + P + Y. Additional published fees: Additional Plan Review (beyond initial + 2 reviews) — $56.00/hour; Inspection Re-Fee — $56.00; Commencing Construction Prior to Permit Issuance — Additional 100% of the Building Fee; Culinary Water Impact Fee — 3/4" meter $6,345.00; 1" meter $6,345.00; 1.5" meter $12,690.00; 2" meter $20,304.00; Wastewater Impact Fee (Non-PID Members, per typical residential connection) — Collection $10,400.00 + Treatment $1,063.00 + Planning $97.00 = $11,560.00 total; Parks Impact Fee — Single-family $1,677.00/household; Multi-Family $1,608.00/household. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the city's official Building Permits page and FAQ, South Salt Lake will review all complete applications within 15 business days, with feedback sent by email to the application's listed contact. Applications remain valid for 180 days.

You'll need: Building Permit Application; Residential Plan Submittal Checklist. See the required-documents checklist on this page for details on each.

South Salt Lake requires 2 inspection(s) for a residential building permit (new construction / addition / remodel), in order: Scheduled Building Inspections, Certificate of Occupancy / Certificate of Completion. Schedule each through South Salt Lake Community Development Department, Building Permits Division ((801) 483-6063, ext. 2).

Apply through South Salt Lake Community Development Department, Building Permits Division at 220 E Morris Avenue, Suite 150, South Salt Lake, UT 84115. Phone: (801) 483-6063, ext. 2, email: permits@sslc.gov, per the official Building Permit Application PDF (revised 05/01/26, sslc.gov/DocumentCenter/View/246); the Building Permits page (sslc.gov/215/Building-Permits) also offers a web contact form. Planning Division: planning@sslc.gov, confirmed via the official ADU Handbook (checked 2026-07-23).. Office hours: Mon–Fri 8:00 AM – 5:00 PM, per South Salt Lake's official Building Department contact listing. Inspection scheduling by phone at (801) 483-6032; Right-of-Way, Demolition, and Sign Permits handled via ext. 3.. Official information: https://sslc.gov/215/Building-Permits.

South Salt Lake, Utah has adopted: International Building Code (IBC) and International Residential Code (IRC), as adopted by the State of Utah and published by the International Code Council (ICC), adopted as the Building Code of South Salt Lake City together with Utah Administrative Code Rule R156-56, per South Salt Lake Municipal Code § 8.10.010 (Ord. No. 2020-06, § VI, 6-3-2020). Local amendments include: Appendix J of the 2012 IBC adopted with an added grading-permit requirement (§8.10.010.A); Appendix P of the 2006 IRC adopted (§8.10.010.B).; International Fire Code (IFC), as adopted by the State of Utah and published by ICC, adopted as the Fire Code of South Salt Lake City, including Appendix D, per Municipal Code § 8.10.020.; International Mechanical Code (IMC) and International Fuel Gas Code (IFGC), as adopted by the State of Utah and published by ICC, adopted as the Mechanical Code of South Salt Lake City, per Municipal Code § 8.10.040.; International Plumbing Code (IPC), as adopted by the State of Utah and published by ICC, adopted as the city's Plumbing Code, with Sections 106.1 and 107.1 of the 2012 IPC locally amended to require permits/fees per the consolidated fee schedule, per Municipal Code § 8.10.070.; National Electrical Code (NEC), as adopted by the National Fire Protection Association and the State of Utah, adopted as the Electrical Code of South Salt Lake City including all city and state amendments, per Municipal Code § 8.10.080.; Uniform Housing Code, 1997 edition (International Conference of Building Officials), adopted as the Housing Code of South Salt Lake City, per Municipal Code § 8.10.050.; Uniform Administrative Code (International Conference of Building Officials) adopted, with fee chapters applied only to the extent they do not conflict with South Salt Lake's own code, per Municipal Code § 8.10.060.; Uniform Code for Building Conservation (International Conference of Building Officials), adopted with all appendices, per Municipal Code § 8.10.090.; Uniform Code for the Abatement of Dangerous Buildings, 1997 edition (International Conference of Building Officials), adopted per Municipal Code § 8.10.100.; All technical codes above are adopted by reference except where they conflict with Utah Code Title 15A and the technical codes adopted therein (the statewide framework), per Municipal Code § 8.10.010.F.. Local amendments apply — see the South Salt Lake overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Salt Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.