Commercial Building Permit in South Salt Lake, Utah

Required for new commercial construction and structural work in South Salt Lake, regulated by the city's adopted IBC (Municipal Code § 8.10.010) and reviewed against the city's own published Commercial Plan Submittal Checklist. The Total Building Permit Fee uses the same city-wide valuation formula as the Residential Building Permit — Building Fee (B) = local multiplier x Gross ICC Building Valuation Data (ICCBVD) valuation; Plan Check Fee (P) = B x 0.65; State Surcharge Fee (Y) = B x 0.01 — per Consolidated Fee Schedule § 3.11.040.A.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial construction or structural work regulated by the city's adopted IBC (Municipal Code § 8.10.010) and International Fire Code (§ 8.10.020)
  • Complete application submitted through the city's Building Permits process (220 E Morris Avenue, Suite 150)
  • Commercial Plan Submittal Checklist items addressed: cover sheet with code/occupancy analysis, plan criteria (allowable areas/heights, occupancy separations, egress, rated walls/openings), site plan, structural sheets, plumbing/mechanical/electrical plans, and — where applicable — a geotechnical (soils) report and civil engineering plans (roads, utilities, storm drainage)
  • Plan Check Fee due at time of building permit application; Building Fee and State Surcharge Fee due prior to permit issuance

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (Building Fee + Plan Check Fee + State Surcharge Fee)South Salt Lake Consolidated Fee Schedule § 3.11.040.A (Ord. No. 2020-02, § V(Exh. D), 1-8-2020, as amended through Ord. No. 2025-17, § 1(Exh. A), 5-28-2025) — this is the same city-wide valuation-based formula used for the Residential Building Permit; South Salt Lake does not publish a separate commercial-only formula. No fixed local multiplier value was published in the fee schedule text itself.
Building Fee (B) = local multiplier x Gross ICCBVD Valuation; Plan Check Fee (P) = B x 0.65; State Surcharge Fee (Y) = B x 0.01; Total = B + P + Y
Additional Plan Review (beyond initial + 2 reviews)South Salt Lake Consolidated Fee Schedule § 3.11.040.A: Building/Plan Check Fees include an initial review plus two subsequent reviews at no charge; additional hourly fees beyond that are $56.00/hour.
$56.00/hour
Inspection Re-FeeSouth Salt Lake Consolidated Fee Schedule § 3.11.040.A.
$56.00
Commencing Construction Prior to Permit IssuanceSouth Salt Lake Consolidated Fee Schedule § 3.11.040.A.
Additional 100% of the Building Fee

Review timeline

Plan reviewSouth Salt Lake’s published plan-review target
15–15 business days

How long did your Commercial Building Permit permit actually take in South Salt Lake?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Structural

    Verified against the submitted structural sheets and specifications before concrete pour, per the Commercial Plan Submittal Checklist.

  2. 2

    MEP Rough-In

    Plumbing, mechanical, and electrical rough-in verified against the submitted DWV isometric, equipment schedule, and service one-line diagram.

  3. 3

    Fire System

    Deferred-submittal fire protection systems (automatic fire sprinkler, fire pump, standpipe, fire alarm, clean agent/dry chemical systems) inspected per the Commercial Plan Submittal Checklist's Fire section.

  4. 4

    Scheduled Building Inspections / Final

    Scheduled by calling (801) 483-6032, per the city's official Building Permits FAQ. Certificate of Occupancy issued once work is found compliant.

See the full South Salt Lake inspection guide — scheduling & re-inspection fees →

Tips

  • South Salt Lake's Commercial Plan Submittal Checklist requires a design professional stamp and signature for plans 3,000 sq ft or more.
  • The city commits to reviewing all complete building permit applications — commercial included — within 15 business days, per its official FAQ.
  • Starting construction before permit approval triggers an additional fee equal to 100% of the Building Fee, separate from any code-violation penalties, per Consolidated Fee Schedule § 3.11.040.A.
  • Building/Plan Check Fees include an initial review plus two subsequent reviews at no extra charge; additional review beyond that is billed at $56.00/hour.

Frequently asked questions

South Salt Lake requires a commercial building permit for: New commercial construction or structural work regulated by the city's adopted IBC (Municipal Code § 8.10.010) and International Fire Code (§ 8.10.020); Complete application submitted through the city's Building Permits process (220 E Morris Avenue, Suite 150); Commercial Plan Submittal Checklist items addressed: cover sheet with code/occupancy analysis, plan criteria (allowable areas/heights, occupancy separations, egress, rated walls/openings), site plan, structural sheets, plumbing/mechanical/electrical plans, and — where applicable — a geotechnical (soils) report and civil engineering plans (roads, utilities, storm drainage); Plan Check Fee due at time of building permit application; Building Fee and State Surcharge Fee due prior to permit issuance. If your project isn't listed, confirm with South Salt Lake Community Development Department, Building Permits Division at (801) 483-6063, ext. 2 before starting work.

In South Salt Lake, the published Building Permit Fee (Building Fee + Plan Check Fee + State Surcharge Fee) is: Building Fee (B) = local multiplier x Gross ICCBVD Valuation; Plan Check Fee (P) = B x 0.65; State Surcharge Fee (Y) = B x 0.01; Total = B + P + Y. Additional published fees: Additional Plan Review (beyond initial + 2 reviews) — $56.00/hour; Inspection Re-Fee — $56.00; Commencing Construction Prior to Permit Issuance — Additional 100% of the Building Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the city's official Building Permits FAQ, South Salt Lake will review and provide feedback on all complete applications — commercial included — within 15 business days.

You'll need: Building Permit Application; Commercial Plan Submittal Checklist; COM Check (Energy Analysis); Structural Sheets, Specifications and Details. Depending on your project, South Salt Lake may also ask for: Geo Tech Report (Soils Engineering Analysis). See the required-documents checklist on this page for details on each.

South Salt Lake requires 4 inspection(s) for a commercial building permit, in order: Foundation / Structural, MEP Rough-In, Fire System, Scheduled Building Inspections / Final. Schedule each through South Salt Lake Community Development Department, Building Permits Division ((801) 483-6063, ext. 2).

Apply through South Salt Lake Community Development Department, Building Permits Division at 220 E Morris Avenue, Suite 150, South Salt Lake, UT 84115. Phone: (801) 483-6063, ext. 2, email: permits@sslc.gov, per the official Building Permit Application PDF (revised 05/01/26, sslc.gov/DocumentCenter/View/246); the Building Permits page (sslc.gov/215/Building-Permits) also offers a web contact form. Planning Division: planning@sslc.gov, confirmed via the official ADU Handbook (checked 2026-07-23).. Office hours: Mon–Fri 8:00 AM – 5:00 PM, per South Salt Lake's official Building Department contact listing. Inspection scheduling by phone at (801) 483-6032; Right-of-Way, Demolition, and Sign Permits handled via ext. 3.. Official information: https://sslc.gov/215/Building-Permits.

South Salt Lake, Utah has adopted: International Building Code (IBC) and International Residential Code (IRC), as adopted by the State of Utah and published by the International Code Council (ICC), adopted as the Building Code of South Salt Lake City together with Utah Administrative Code Rule R156-56, per South Salt Lake Municipal Code § 8.10.010 (Ord. No. 2020-06, § VI, 6-3-2020). Local amendments include: Appendix J of the 2012 IBC adopted with an added grading-permit requirement (§8.10.010.A); Appendix P of the 2006 IRC adopted (§8.10.010.B).; International Fire Code (IFC), as adopted by the State of Utah and published by ICC, adopted as the Fire Code of South Salt Lake City, including Appendix D, per Municipal Code § 8.10.020.; International Mechanical Code (IMC) and International Fuel Gas Code (IFGC), as adopted by the State of Utah and published by ICC, adopted as the Mechanical Code of South Salt Lake City, per Municipal Code § 8.10.040.; International Plumbing Code (IPC), as adopted by the State of Utah and published by ICC, adopted as the city's Plumbing Code, with Sections 106.1 and 107.1 of the 2012 IPC locally amended to require permits/fees per the consolidated fee schedule, per Municipal Code § 8.10.070.; National Electrical Code (NEC), as adopted by the National Fire Protection Association and the State of Utah, adopted as the Electrical Code of South Salt Lake City including all city and state amendments, per Municipal Code § 8.10.080.; Uniform Housing Code, 1997 edition (International Conference of Building Officials), adopted as the Housing Code of South Salt Lake City, per Municipal Code § 8.10.050.; Uniform Administrative Code (International Conference of Building Officials) adopted, with fee chapters applied only to the extent they do not conflict with South Salt Lake's own code, per Municipal Code § 8.10.060.; Uniform Code for Building Conservation (International Conference of Building Officials), adopted with all appendices, per Municipal Code § 8.10.090.; Uniform Code for the Abatement of Dangerous Buildings, 1997 edition (International Conference of Building Officials), adopted per Municipal Code § 8.10.100.; All technical codes above are adopted by reference except where they conflict with Utah Code Title 15A and the technical codes adopted therein (the statewide framework), per Municipal Code § 8.10.010.F.. Local amendments apply — see the South Salt Lake overview page for the full list.

Per the city's official Commercial Plan Submittal Checklist, submittals must include a cover sheet with code/occupancy analysis, site plan, structural sheets and specifications, plumbing (DWV isometric, gas piping), mechanical (equipment schedule, ventilation), electrical (service one-line, load calculations), and — where applicable — a geotechnical report, COM Check energy analysis, and civil engineering plans (roads, utilities, storm drainage).

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Salt Lake building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in South Salt Lake.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.